Construction S-Curve & Earned Value Tracker
Planned, earned and actual curves from your schedule, with the cash the client will need.
Try before you buy.
- Free preview: the curves of all your activities on a watermarked chart, the status figures, and the first rows of the monthly data and the cash-flow plan (up to 10).
- Locked until you unlock it: download.
- Unlock: Premium pass, ₹799 for 30 days, a one-time payment that never renews.
Ways to unlock shows how to get the full result.
Printing this result is locked in the free preview.
This browser is not keeping data for this page (private mode or storage switched off). Your project stays only until the tab closes: download a backup on the Activities tab.
Project
Activities
No activities yet. Add them one by one, paste them, or import a CSV or Excel file.
Paste activities from a spreadsheet
Your data
Progress by month
Cumulative % complete of each activity at the end of the month. Leave a field empty to keep the activity’s last figure.
| Activity | Budget | Planned by this month | Last figure | % complete at the month’s end |
|---|
Months recorded
| Month | Earned value to date | Actual cost of the month | Actual cost to date | Open |
|---|
S-curve
Month by month
| Month | PV in the month | PV to date | EV to date | AC to date | SPI | CPI | EV forecast | AC forecast |
|---|
Payment terms
Month-by-month funding
| Month | Basis | Value of work | Tax | Retention | Advance recovered | Bill | Advance / release | Paid in the month | Cumulative |
|---|
Locked in the free preview. Opens the ways to unlock this result.
Locked in the free preview. Batch runs unlock with a pass.
Locked in the free preview. Query results unlock with a pass.
Results are estimates for general information and planning, not financial advice. Banks and institutions may calculate differently (rounding, fees, rate changes). Confirm figures with your lender or a qualified adviser before deciding.
About the Construction S-Curve & Earned Value Tracker
Build the S-curve of a project from its schedule and budget: list the activities with their dates and costs — typed, pasted from a spreadsheet or imported from a CSV or Excel file — and spread each cost evenly, front-loaded, back-loaded or along a bell curve. The tool adds them up month by month into the planned value curve. Then record each month’s percent complete (by activity, or overall) and actual cost: the earned value and actual cost curves follow, with the schedule and cost variances, SPI, CPI and the earned schedule worked out by the same engine as the Earned Value Calculator.
From the status month the tool forecasts the rest — at the planned pace or at the pace so far, at budget or at the cost efficiency so far — and turns it into a month-by-month cash-flow plan for the client’s funding, with a mobilisation advance and its recovery, retention and its release, tax and the delay before bills are paid. The free preview plots all your activities on a watermarked chart with the status figures and the first rows of the tables; a Premium pass unlocks the full tables and the PNG, PDF and Excel exports.
How to use it
- On Activities, add each activity with its start, end and budget, or paste or import them from a CSV or Excel file (activity, start, end or duration, budget). A planner’s CSV schedule brings in the tasks and their dates; then enter each budget. Pick each one’s spread: even, front-loaded, back-loaded or bell.
- On Progress, choose a month and enter each activity’s cumulative % complete at its end (or one overall %) and the actual cost spent in that month. Repeat for each month.
- On S-curve, read the planned, earned and actual curves, the variances and indices, and the forecast. Choose how the rest is forecast: at the planned pace or at the current SPI(t), and at budget or at the CPI so far.
- On Cash flow, set the advance, recovery, retention, tax and payment delay of your contract to see what the client pays each month.
- With a Premium pass, or after unlocking the S-curve, download the chart as PNG, the report as PDF and every table as an Excel workbook; your backup always downloads.
Examples
Foundations, 16 Jan to 16 Mar (60 days), budget ₹9,00,000, even
January 16 days ₹2,40,000 · February 28 days ₹4,20,000 · March 16 days ₹2,40,000
Superstructure, 1 Mar to 30 Jun (122 days), ₹24,00,000, bell
End of March (31 of 122 days): 24,00,000 × 2 × (31/122)² = ₹3,09,916.69; end of April (half the time): ₹12,00,000
BAC ₹60,00,000 · PV ₹15,09,916.69 · EV ₹14,25,000 · AC ₹15,90,000
SPI 0.94, CPI 0.90 · earned schedule 2.85 of 3 months · EAC = BAC ÷ CPI = ₹66,94,736.84 · forecast finish a month late
Common uses
- Contractors and project managers preparing the baseline S-curve that a client or lender asks for with the programme.
- Monthly progress reports with planned, earned and actual curves and the variances behind them.
- Owners and lenders planning how much funding a project needs each month, with advance, retention and payment terms.
- Spotting a slipping project early: SPI(t) and the forecast finish show the delay months before the end.
How the baseline is built
- Each activity runs from its start to its end date, both days counted.
- Its budget is spread with a cumulative profile P(x), x being the share of its time gone: even P(x) = x; front-loaded P(x) = 2x − x²; back-loaded P(x) = x²; bell P(x) = 2x² to the middle and 1 − 2(1 − x)² after it.
- The part in a month = budget × [P(x at the month’s end) − P(x at the month’s start)], rounded on the running total so the months add up exactly to the budget.
- Planned value (PV) of a month = the sum over the activities; its running total is the S-curve and ends at the budget at completion (BAC).
Earned value, the indices and the earned schedule
- Earned value (EV) at a month’s end = Σ budget × % complete, using each activity’s latest figure; or BAC × overall %. Actual cost (AC) = the running total of the monthly costs.
- SV = EV − PV, CV = EV − AC, SPI = EV ÷ PV, CPI = EV ÷ AC, as in NASA’s earned value tutorial and the GAO Cost Estimating and Assessment Guide.
- Earned schedule ES = the months of plan the earned value is worth (whole months whose PV is reached, plus the fraction of the next); SPI(t) = ES ÷ months elapsed keeps telling the truth after the planned finish, when SPI drifts back to 1 (earned schedule).
The forecast
- The work left is done in the order of the baseline, starting from the earned schedule: one month of plan per month (planned pace), or SPI(t) months of plan per month (current pace).
- Its cost: at budget, at the CPI so far, or at CPI × SPI. The estimate at completion is EAC = AC + (BAC − EV) ÷ factor; the variance at completion VAC = BAC − EAC.
- The forecast finish is the month the forecast earned value reaches the budget at completion.
The cash-flow plan
- Value of work each month: the actual cost up to the status month, then the forecast cost; before any progress, the planned value.
- Each month’s bill = value + tax − retention − advance recovery; it is paid the number of months later you set.
- The advance is paid in the first month and recovered at the percentage you set from each bill until it is repaid; a balance still unrecovered when the work ends comes off the bill of the last month of work. Retention is kept from each bill up to its limit and released in one sum after the last month of work.
- The cumulative funding is the money the client needs by each month; it ends at the estimate at completion (plus tax).
Importing a schedule
Paste rows from a spreadsheet, or open a CSV or Excel file whose first row names the columns: activity (or task), start, end (or finish, or a duration in days), budget (or cost), and optionally code and profile. Dates may be written 2026-01-05, 05/01/2026 or 5 Jan 2026, or come as spreadsheet dates. Download the template to see the layout; a bill of quantities with a start and a duration per item imports the same way.
A schedule from a planner (its CSV, with a type column of Task, Phase or Milestone) imports its tasks with their WBS numbers and dates; phases are left out, because their tasks carry the work, and so are milestones. A schedule has no costs, so each imported activity waits for its budget, and the checks name every one still missing.
Sources
- US GAO, Cost Estimating and Assessment Guide — earned value management
- NASA, earned value management tutorial — the formulas of the indices and estimates at completion
- Earned schedule — earned schedule and SPI(t)
The tool plans and reports; contract payments follow the contract’s own terms and certified measurements.
Limitations
- Months are calendar months; working-day calendars, holidays and non-working periods are not modelled.
- Activities are spread on their own dates: dependencies between them are not scheduled or checked.
- One currency and one status per month: costs in other currencies need converting first.
- The forecast follows the baseline’s order of work; a re-planned programme needs a new baseline.
- Your project is kept in this browser on this device: download a backup to move it or keep it safe.
Privacy
The activities, progress and payment terms are kept in this browser’s storage on your device and never sent to MySmartCoPilot or anyone else. Imported files are read on the device; the chart, the report and the workbook are made on it.
Frequently asked questions
What do I get without a pass?
Without a pass, Construction S-Curve & Earned Value Tracker shows the curves of all your activities on a watermarked chart, the status figures, and the first rows of the monthly data and the cash-flow plan (up to 10). Until you unlock it, the result can’t be downloaded. A Premium or Ultimate pass, a one-time payment that never renews, unlocks the full result. The pricing page lists the passes and their prices.
What is an S-curve in construction?
The running total of a project’s planned cost (or work) plotted month by month. Work starts slowly, speeds up in the middle and tails off, so the curve looks like an S. Plotting earned value and actual cost on it shows at a glance whether the project is ahead or behind and over or under budget.
Which profile should I use for an activity?
Even suits steady work such as masonry. Front-loaded suits activities that spend early — mobilisation, material purchases, excavation. Back-loaded suits work that is billed or finished late — finishes, testing, handover. Bell suits activities that ramp up and down, such as a structural frame.
How is the percent complete turned into earned value?
Earned value = each activity’s budget × its cumulative % complete, added up. Enter the cumulative figure at the end of the month (not the progress made in the month). An activity without a new figure keeps its last one.
Why does the forecast finish differ from the planned finish?
Because the work earned so far is worth fewer months of plan than have passed (SPI(t) below 1). At the planned pace the rest still takes its planned time, so the delay so far carries on to the end; at the current pace the rest goes slower too.
Can I use this with the Earned Value Calculator?
Yes: both use the same formulas. The Earned Value Calculator gives the figures of one status from totals; this tool builds the activity-loaded baseline, keeps the month-by-month history and plans the cash flow.
Where is my project kept?
In this browser on your device. You don’t need an account; download a backup from the Activities tab to keep it safe or open it on another device.