Bar Bending Schedule Maker for Indian Sites (IS 2502)
Every floor and member of a building in one bar bending schedule, with a cutting plan.
Try before you buy.
- Free preview: the first bar marks of each floor (up to 10) in full, the first cutting patterns, and the schedule and tags as marked page images, with other figures hidden.
- Locked until you unlock it: download and copy.
- Unlock: Premium pass, ₹799 for 30 days or ₹249 for 1 week, a one-time payment that never renews. Unlock: Premium pass, $19.99 for 30 days or $7.99 for 1 week, a one-time payment that never renews.
Ways to unlock shows how to get the full result.
Printing this result is locked in the free preview.
This browser is not keeping data for this page (private mode or storage switched off). Your work stays only until the tab closes: download a backup on the Project tab.
Project
Schedule settings
Planned steel, kg per m³ of concrete optional, from your estimate
Letterhead for the schedule PDF
Your data
Projects are kept in this browser on this device. Download a backup now and then; restore it here or on another device.
Floors
Members
A member stands for its identical members (C1–C4: 4). Add its bar marks one by one, or fill them from a template and edit them. Dimensions in mm, as on the drawing (outside dimensions; links from the member size and cover).
No members on this floor yet.
Schedule
Free preview: the cutting length, numbers, length and weight of the first bar marks of each floor show here; the rest of the schedule, its totals and the summaries below show once this schedule is unlocked. Your floors, members and bar marks always show.
Steel by diameter
| Diameter | Bars | Length (m) | Weight (kg) | Weight (t) |
|---|
Steel by floor and diameter (kg)
Steel by element and kg per m³
| Element | Steel (kg) | Concrete (m³) | kg per m³ | Planned | Difference |
|---|
Notes
Cutting plan
Documents
Send steel to the reconciliation: opens the site material reconciliation statement with this schedule’s steel by diameter.
Locked in the free preview. Opens the ways to unlock this result.
Locked in the free preview. Batch runs unlock with a pass.
Locked in the free preview. Query results unlock with a pass.
Results are estimates from the formulas shown, not a professional design or certification. Have a qualified engineer verify anything safety-critical (structures, electrical installations, gas or pressure systems).
About the Bar Bending Schedule Maker for Indian Sites (IS 2502)
Make the bar bending schedule of a whole building: floors (with how many identical floors), the members on each floor — footings, columns, beams, slabs, stairs, walls — with how many identical members, and their bar marks. Each bar mark is worked out with the IS 2502 shape formulas, hook and bend allowances and cutting lengths to the next 25 mm, IS 456 laps where a bar is longer than a stock bar and IS 1786 masses, then multiplied by members and floors.
With a Premium pass you get the schedule floor by floor with a sketch of every bar shape, steel by diameter, floor by diameter and element, a kg per m³ check against the steel you planned, a cutting plan that packs each diameter’s pieces into 12 m stock bars with the offcuts it leaves, bar tags for the bundles, a schedule PDF on your letterhead and an Excel workbook with live formulas. Steel by diameter can be sent on to the material reconciliation statement. The free preview works on your own drawings: the first bar marks of each floor with their cutting lengths, numbers and weights, the first cutting patterns, and the documents as marked page images.
How to use it
- On Project, enter the project and drawings, the steel grade, concrete grade (for laps), stock bar length and the kg/m³ you planned for each element, if any.
- On Members, add the floors — set how many identical floors one stands for — and on each floor the members: element, name (C1–C4), how many identical members and, for the kg/m³ check, the concrete in one member.
- Add each member’s bar marks — shape, diameter, dimensions from the drawing and the number per member (directly or as a spacing over a length) — or fill them from a slab, beam, column, footing or stair template and edit them.
- Check the Schedule (totals, notes, kg/m³) and the Cutting plan, then — with a Premium pass, or after unlocking this schedule — download the schedule PDF, the bar tags and the Excel workbook on Documents.
Examples
6 bars of 16 mm, 3,650 mm long (with the lap) · 8 mm ties, 135° hooks, 230 × 450 mm, cover 40, at 150 over 3 m
16 mm: 6 × 4 × 3 = 72 bars × 3.65 m = 262.8 m × 1.58 = 415.22 kg · ties: 2 × (354 + 134) + 24 × 8 = 1,168 → 1,175 mm, 21 × 4 × 3 = 252 ties = 116.96 kg
72 pieces of 3,650 mm
3 pieces from each bar (10,950 mm) → 24 stock bars, a 1,050 mm offcut from each (8.75%)
Column steel 532.18 kg in 3.726 m³ of concrete · planned 150 kg/m³
142.8 kg/m³, 4.8% below the plan
Common uses
- Site engineers making the BBS of a G+2 or G+4 building from the structural drawings.
- Contractors ordering steel by diameter and planning the cutting of 12 m bars.
- Bar-bending yards tagging bundles by member and floor.
- Quantity surveyors checking steel per m³ against the estimate.
Cutting lengths (IS 2502)
The lengths are those of the bar bending schedule calculator: measured along the centre line with the IS 2502 Table II hook allowance H and bend allowance B (internal radius 4d for TMT/HYSD bars, 2d for mild steel), L-bars A + E − ½R − d, U-bars with the same deduction at each bend, cranks + D·tan(θ/2) each, closed links 2(A + E) + 24d with 135° hooks, rings π(D + d) + 2H and helices N·π(D + d) + 8d. Cutting lengths go up to the next 25 mm (cl. 5.1.1). Bars longer than a stock bar get IS 456 cl. 26.2.5.1 laps (none above 32 mm: couplers are counted instead). Masses are IS 1786 Table 1 (0.395, 0.617, 0.888, 1.58, 2.47 and 3.85 kg/m for 8 to 25 mm) or D²/162.
Floors, members and totals
Each bar mark’s total number = number per member × identical members × identical floors. The schedule adds the bars, lengths and weights by diameter, by floor, by floor and diameter, and by element (footings, columns, beams, slabs, stairs, walls). Enter the concrete in one member to get the steel per m³ of each element and compare it with the figure you planned — from your estimate or the steel quantity calculator; a large difference often means a missing or doubled bar mark.
The cutting plan
Each diameter’s pieces are cut from stock bars (12 m unless you change it). A bar longer than a stock bar takes whole stock bars and a remainder; its laps are already in its cutting length. The other pieces are packed longest first, by first-fit and by best-fit, and the plan with fewer stock bars is kept. Every stock bar’s pieces form a cutting pattern — “24 bars: 3 × 3,650 mm, offcut 1,050 mm” — and offcuts at least as long as you set (1 m to start with) are listed as usable; the rest is scrap. You can allow for a blade loss at each cut. The plan is close to the fewest bars but not guaranteed to be the least possible, and offcuts of one diameter are not used for another.
Documents and workbook
The schedule PDF (A4 or A3 landscape, with your letterhead) lists every floor and member with a sketch of each bar, then the totals, the kg/m³ check, the cutting plan and prepared / checked signatures. Bar tags come eight to an A4 page with cut lines. The Excel workbook has the schedule with total bars, lengths and weights as formulas, the bar masses, the summaries by diameter, floor and element as SUMIF formulas, and the cutting patterns.
Sources
- IS 2502, Code of practice for bending and fixing of bars for concrete reinforcement — archive.org
- IS 1786, High strength deformed steel bars and wires for concrete reinforcement, Table 1 — archive.org
- IS 456, Plain and reinforced concrete, cl. 26.2 (development length and laps) — archive.org
Limitations
- A scheduling aid, not a structural design: bar sizes, spacings, laps and their positions come from the drawings and your engineer.
- Special shapes, other bend radii and seismic detailing (IS 13920) may need their own allowances: use the overrides of each bar.
- The cutting plan packs each diameter separately and does not reuse offcuts across diameters or jobs; with more than 20,000 pieces of one diameter it counts by length.
- Projects are kept in this browser on this device: download a backup to move them or keep them safe.
Privacy
On this device: nothing is sent
Projects, members and bars are kept in this browser’s storage on your device and never sent to MySmartCoPilot or anyone else. The PDFs and the workbook are made on the device.
Frequently asked questions
What do I get without a pass?
Without a pass, Bar Bending Schedule Maker for Indian Sites (IS 2502) shows the first bar marks of each floor (up to 10) in full, the first cutting patterns, and the schedule and tags as marked page images, with other figures hidden. Until you unlock it, the result can’t be downloaded or copied. A Premium or Ultimate pass, a one-time payment that never renews, unlocks the full result. The pricing page lists the passes and their prices.
How is this different from the bar bending schedule calculator?
The calculator makes one flat schedule. The maker organises a whole building by floors and members with repeat counts, adds the floor and element totals, the kg/m³ check, the cutting plan, bar tags, a schedule PDF on your letterhead and an Excel workbook, and keeps several projects.
How do identical floors work?
Set “identical floors” on a floor to the number of floors it stands for — 3 for three typical floors — and every bar on it is counted three times in the totals, the cutting plan and the tags.
Why does the cutting plan need more stock bars than total length ÷ 12 m?
Because pieces do not fit a stock bar exactly: three 3,650 mm pieces use 10,950 mm and leave 1,050 mm. The plan counts the stock bars you really need and shows the offcuts.
What kg per m³ should I expect?
It depends on the design, span, loads and seismic zone, so the tool does not assume a figure: enter the one from your estimate or structural design and compare. The steel quantity calculator can estimate one from steel percentages.
Can the steel go into the material reconciliation?
Yes: with a pass, or once this schedule is unlocked, “Send steel to the reconciliation” on Documents opens the site material reconciliation statement with this schedule’s steel by diameter as the theoretical quantity.