Project Management & Agile  Module 4 – Scheduling: networks, critical path and Gantt charts

Three-point estimates and schedule risk analysis

Estimate durations as ranges, compare PERT and triangular weighting, run a seeded Monte Carlo analysis for P50 and P80 dates, and set contingency from it.

  • Advanced
  • 10 minutes
  • Examples run with Python 3.14.8
  • By MySmartCoPilot
Free lesson, Pro answers: 10 minutes
Free: the whole lesson. With a pass: the model answers to its 2 interview questions.

What you will learn

  • Estimate activity ranges with three-point estimates and choose triangular or PERT weighting
  • Calculate a single-path PERT estimate and the chance of meeting a date from it
  • Interpret P50 and P80 finish dates from a Monte Carlo schedule risk analysis
  • Explain merge bias and why parallel paths make finishing on time less likely
  • Set schedule contingency from the analysis instead of padding

Before you start

What you’ll learn · Before you start

What you will learn

  • Estimate activity ranges with three-point estimates and choose triangular or PERT weighting
  • Calculate a single-path PERT estimate and the chance of meeting a date from it
  • Interpret P50 and P80 finish dates from a Monte Carlo schedule risk analysis
  • Explain merge bias and why parallel paths make finishing on time less likely
  • Set schedule contingency from the analysis instead of padding

Before you start

On this page

The tech fest’s critical path says 38 working days, yet in 10,000 simulated runs of the same plan it was over by day 38 in only 14.7 % of them, and in 2.7 % with a different but equally reasonable way of reading the estimates. A date computed from single durations is the date of a plan in which nothing goes wrong.

You will turn each estimate into a range, add the ranges along a path with PERT, run a seeded Monte Carlo analysis of the whole network, see why paths that meet make lateness more likely, and set the contingency an 80 % date needs.

Three numbers describe an estimate better than one

Ask the sponsor team how long signing sponsors will take and the honest answer is a range: 8 days if every company replies at once, 10 most likely, 16 if two of them stall. A three-point estimate: An estimate given as three durations, optimistic, most likely and pessimistic, so that its range and its shape can be used in a risk analysis. records exactly that: optimistic (O), most likely (M) and pessimistic (P). GAO’s schedule guide asks for such fields in the schedule before a risk analysis, gathered from the people who know the work, and anonymously where that helps them speak freely. The fest’s ranges are skewed to the right, as most schedule ranges are: things can go much more wrong than right.

Two ways of weighting the three numbers are common. PERT, from the 1959 paper of Malcolm, Roseboom, Clark and Fazar, gives the most likely value four times the weight of each extreme:

te=O+4M+P6,σ=P−O6t_e = \frac{O + 4M + P}{6}, \qquad \sigma = \frac{P - O}{6}

In words: the expected time is a weighted average, and the standard deviation is one sixth of the range. For signing sponsors, (8 + 40 + 16) ÷ 6 = 10.67 days, with σ = 8 ÷ 6 = 1.33. A triangular distribution weights the three equally, (O + M + P) ÷ 3, which gives 11.33 days: more weight on the long tail, so later dates. The program below prints both for every activity, then uses them:

Ranges, the PERT path sum and two Monte Carlo runs of the fest Python · risk.py
"""A schedule risk analysis of the tech fest: three-point estimates, the single-path PERT sum and a Monte Carlo run.

Each activity has an optimistic (O), a most likely (M) and a pessimistic (P) duration in working days; M is the
duration the critical path lesson used. PERT weights them (O + 4M + P) / 6 with a standard deviation of (P - O) / 6
(Malcolm, Roseboom, Clark and Fazar, Operations Research, 1959); a triangular distribution weights them equally,
(O + M + P) / 3. The Monte Carlo run draws every activity 10,000 times from each distribution, with a fixed seed so
that every run of this program prints the same numbers, and recalculates the whole network each time.
"""
import math
import random
from statistics import NormalDist

# id: (name, O, M, P, [(predecessor, type, lag)])
FEST = {
    "A": ("Authorise plan and budget", 2, 3, 5, []),
    "B": ("Book the auditorium", 1, 2, 4, [("A", "FS", 0)]),
    "C": ("Prepare sponsor packages", 4, 5, 8, [("A", "FS", 0)]),
    "D": ("Sign sponsors", 8, 10, 16, [("C", "FS", 0)]),
    "E": ("Design the coding contest", 6, 8, 12, [("A", "FS", 0)]),
    "F": ("Build the robotics arena", 10, 12, 18, [("D", "FS", 0)]),
    "G": ("Line up speakers", 4, 6, 9, [("B", "FS", 0)]),
    "H": ("Build the registration form", 3, 4, 6, [("E", "FS", 0)]),
    "I": ("Run the publicity campaign", 9, 10, 13, [("H", "SS", 2)]),
    "J": ("Print posters", 2, 3, 5, [("G", "FS", 0)]),
    "K": ("Plan crowd control and first aid", 4, 5, 7, [("B", "FS", 0)]),
    "L": ("Set up sound, lights and stage", 2, 2, 4, [("F", "FS", 0), ("K", "FS", 0)]),
    "M": ("Hold the fest", 2, 2, 2, [("L", "FS", 0), ("H", "FS", 0), ("J", "FS", 0), ("I", "FF", 0)]),
    "N": ("Close the accounts and report", 3, 4, 7, [("M", "FS", 0)]),
}
RUNS, SEED = 10_000, 2026
SUCC = {a: [(s, k, lag) for s in FEST for p, k, lag in FEST[s][4] if p == a] for a in FEST}


def finish_and_critical(dur):
    es, ef = {}, {}
    for a, (*_, links) in FEST.items():
        start = 0.0
        for p, kind, lag in links:
            start = max(start, {"FS": ef[p] + lag, "SS": es[p] + lag, "FF": ef[p] + lag - dur[a]}[kind])
        es[a], ef[a] = start, start + dur[a]
    end = max(ef.values())
    ls, lf = {}, {}
    for a in reversed(list(FEST)):
        finish = end
        for s, kind, lag in SUCC[a]:
            finish = min(finish, {"FS": ls[s] - lag, "SS": ls[s] - lag + dur[a], "FF": lf[s] - lag}[kind])
        lf[a], ls[a] = finish, finish - dur[a]
    return end, [a for a in FEST if ls[a] - es[a] < 1e-9]


def pert_draw(rng, o, m, p):
    """A draw from the PERT (beta) distribution with the same O, M and P."""
    if p == o:
        return float(o)
    alpha = 1 + 4 * (m - o) / (p - o)
    beta = 1 + 4 * (p - m) / (p - o)
    return o + (p - o) * rng.betavariate(alpha, beta)


def percentile(xs, q):
    xs = sorted(xs)
    return xs[min(len(xs) - 1, int(math.ceil(q * len(xs))) - 1)]


most_likely = {a: FEST[a][2] for a in FEST}
end_m, path = finish_and_critical(most_likely)
print(f"With the most likely durations: finish after {end_m:.0f} days, critical path {' '.join(path)}")
print(f"{'Id':<3}{'O':>3}{'M':>3}{'P':>3}{'PERT mean':>11}{'PERT sd':>9}{'Triangular mean':>17}")
for a, (_, o, m, p, _) in FEST.items():
    print(f"{a:<3}{o:>3}{m:>3}{p:>3}{(o + 4 * m + p) / 6:>11.2f}{(p - o) / 6:>9.2f}{(o + m + p) / 3:>17.2f}")
mean = sum((FEST[a][1] + 4 * FEST[a][2] + FEST[a][3]) / 6 for a in path)
sd = round(math.sqrt(sum(((FEST[a][3] - FEST[a][1]) / 6) ** 2 for a in path)), 1)
curve = NormalDist(mean, sd)
print(f"Single-path PERT on {''.join(path)}: mean {mean:.1f} days, sd {sd}")
print(f"  normal curve: chance of finishing by day 38 {curve.cdf(38):.1%}, P80 {curve.inv_cdf(0.8):.1f} days")
print()
for label, draw in (("Triangular", lambda r, o, m, p: r.triangular(o, p, m)), ("PERT (beta)", pert_draw)):
    rng = random.Random(SEED)
    ends, critical = [], dict.fromkeys(FEST, 0)
    for _ in range(RUNS):
        dur = {a: draw(rng, FEST[a][1], FEST[a][2], FEST[a][3]) for a in FEST}
        end, crit = finish_and_critical(dur)
        ends.append(end)
        for a in crit:
            critical[a] += 1
    on_time = sum(1 for e in ends if e <= 38) / RUNS
    p50, p80 = percentile(ends, 0.5), percentile(ends, 0.8)
    print(f"Monte Carlo, {label}, {RUNS} runs, seed {SEED}:")
    print(f"  P50 {p50:.1f} days, P80 {p80:.1f} days, finished by day 38 in {on_time:.1%} of runs")
    print(f"  contingency after the plan's day {end_m:.0f}: {math.ceil(p50) - end_m:.0f} days for a 50 % date "
          f"(day {math.ceil(p50)}), {math.ceil(p80) - end_m:.0f} days for an 80 % date (day {math.ceil(p80)})")
    top = sorted(critical.items(), key=lambda kv: -kv[1])
    print("  on the critical path in this share of runs: " + ", ".join(f"{a} {n / RUNS:.0%}" for a, n in top if n))

Output

With the most likely durations: finish after 38 days, critical path A C D F L M N
Id   O  M  P  PERT mean  PERT sd  Triangular mean
A    2  3  5       3.17     0.50             3.33
B    1  2  4       2.17     0.50             2.33
C    4  5  8       5.33     0.67             5.67
D    8 10 16      10.67     1.33            11.33
E    6  8 12       8.33     1.00             8.67
F   10 12 18      12.67     1.33            13.33
G    4  6  9       6.17     0.83             6.33
H    3  4  6       4.17     0.50             4.33
I    9 10 13      10.33     0.67            10.67
J    2  3  5       3.17     0.50             3.33
K    4  5  7       5.17     0.50             5.33
L    2  2  4       2.33     0.33             2.67
M    2  2  2       2.00     0.00             2.00
N    3  4  7       4.33     0.67             4.67
Single-path PERT on ACDFLMN: mean 40.5 days, sd 2.2
  normal curve: chance of finishing by day 38 12.8%, P80 42.4 days

Monte Carlo, Triangular, 10000 runs, seed 2026:
  P50 42.9 days, P80 45.4 days, finished by day 38 in 2.7% of runs
  contingency after the plan's day 38: 5 days for a 50 % date (day 43), 8 days for an 80 % date (day 46)
  on the critical path in this share of runs: A 100%, C 100%, D 100%, F 100%, L 100%, M 100%, N 100%
Monte Carlo, PERT (beta), 10000 runs, seed 2026:
  P50 40.4 days, P80 42.5 days, finished by day 38 in 14.7% of runs
  contingency after the plan's day 38: 3 days for a 50 % date (day 41), 5 days for an 80 % date (day 43)
  on the critical path in this share of runs: A 100%, C 100%, D 100%, F 100%, L 100%, M 100%, N 100%

Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 risk.py

Choose the weighting from how the estimates were made. If M is the value people are confident about and the extremes are rare, PERT fits; if the extremes are as real as M, or the estimators doubt their M, the triangular reading is the more cautious choice. Either way, say which one the analysis used.

Adding the path gives a first answer

The quickest analysis adds up the critical path. Expected times add, and so do variances, the squares of σ, when the activities are independent. For A, C, D, F, L, M and N that gives a mean of 40.5 days and a standard deviation of 2.2, so a normal curve can say how likely day 38 is. Drag the limits or the mean to see how the chance moves:

Interactive · change it and see Chance that the fest's critical path is done by day 38 Set the mean and the standard deviation, then the two ends of the range. The shaded area is the probability that a value falls between them.
The bell curve with the range shaded: density against x.35404500.050.10.150.2xdensitydensityμ

For a normal distribution with mean 40.5 and standard deviation 2.2, the probability of a value between 30 and 38 is 0.1279 (12.8 %), from z = −4.77 to z = −1.14.

P(30 ≤ X ≤ 38) 0.1279
z-score of a −4.77
z-score of b −1.14
The numbers as a table
Probability within k standard deviations of the mean
RangeProbability
μ ± 1σ0.6827
μ ± 2σ0.9545
μ ± 3σ0.9973

The shaded area from day 30 to day 38 is about 0.128: a 12.8 % chance, the same as the program’s single-path line. The sum ignores every other path, though. It assumes that the critical path stays critical, and that nothing at a merge point can delay the finish. Both assumptions are tested by simulating the whole network; in the course plan of NPTEL’s Project Management for Managers from IIT Roorkee, week 9 is given to probability models in networks.

Adding standard deviations instead of variances

Wrong: 0.50 + 0.67 + 1.33 + 1.33 + 0.33 + 0 + 0.67 = 4.83 days. Right: add the variances, (P − O)² ÷ 36 for each activity, (9 + 16 + 64 + 64 + 4 + 0 + 16) ÷ 36 = 4.81, and take the square root, 2.19, about 2.2. Uncertainties partly cancel when independent activities are added.

Checkpoint

Check: Three-point estimates and weighting · The single-path PERT sum

  1. Question 1 of 2 Building the robotics arena has O = 10, M = 12 and P = 18 days. What is its PERT expected duration, in days?

    Type a number.

    Show the answer: Question 1 of 2

    Answer: 12.67 days (anything from 12.66 to 12.68 counts)

    (10 + 4 × 12 + 18) ÷ 6 = 76 ÷ 6 = 12.67 days, as the program's table shows for F.

  2. Question 2 of 2 Two independent activities on a path have standard deviations of 3 and 4 days. What is the standard deviation of their total, in days?

    Type a number.

    A hint

    Add the variances, then take the square root.

    Show the answer: Question 2 of 2

    Answer: 5 days

    Variances add: 3² + 4² = 9 + 16 = 25, and √25 = 5 days, not 3 + 4 = 7.

A Monte Carlo run recalculates the whole network thousands of times

A Monte Carlo simulation: A method that draws every uncertain input from its range many times, recalculates the model each time and reports the spread of the results. draws a duration for every activity from its range, recalculates the network with its links, records the finish, and repeats. GAO’s eighth best practice is this kind of schedule risk analysis: An analysis that simulates a schedule's uncertain durations and risks to give the chance of meeting each key date and the activities that most often drive the finish., and its checklist asks for the confidence level of the key dates and for the activities that most often ended up on the critical path. The program ran 10,000 times for each weighting, with seed 2026, so every run of the page’s program prints the same numbers.

With PERT weighting, half the runs were done by day 40.4, the The duration that half of the simulated runs met or beat; P80 is likewise the duration that 80 % of the runs finished within., and 80 % by day 42.5, the P80; 14.7 % finished by day 38. With triangular weighting the same ranges gave a P50 of 42.9, a P80 of 45.4 and only 2.7 % by day 38. The critical path stayed A, C, D, F, L, M and N in every run: the events chain’s 11 days of float were never used up, which is why the PERT run agrees so closely with the single-path sum.

Method P50 P80 Finished by day 38
Single-path PERT, normal curve 40.5 42.4 12.8 %
Monte Carlo, PERT weighting 40.4 42.5 14.7 %
Monte Carlo, triangular weighting 42.9 45.4 2.7 %

The single-path P80 is the normal curve’s 80th percentile, 42.4, which the program prints with its chance of day 38. The spread between the rows is the honest answer to “when will the fest be over”: a range, read at the confidence the sponsor chooses.

Merge bias: parallel paths make on time less likely

Where paths join, the event waits for the latest of them. GAO’s guide calls the added risk at those points merge bias: The extra risk where parallel paths join: the joined event waits for the latest path, so it is later than any one path suggests., and gives an example: two paths that are each 60 % likely to be on time are both on time only 36 % of the time. The program below runs paths of 8 to 12 days, each on time by day 10 half the time, into one milestone:

One to four paths of even odds meeting at a milestone Python · merge.py
"""Merge bias: parallel paths that each have an even chance of finishing on time rarely all do.

Each path takes 8 to 12 days, most likely 10, drawn from a triangular distribution, so each finishes within 10 days
half the time. A milestone that waits for all of them is on time only when every path is. The runs use a fixed seed,
so every run of this program prints the same numbers.
"""
import random

RUNS, SEED, TARGET = 10_000, 7, 10
rng = random.Random(SEED)
print(f"Each path: 8 to 12 days, most likely 10; the milestone is due on day {TARGET}")
print(f"{'Paths':>5}{'Each path on time':>19}{'Milestone on time':>19}{'Exact':>8}{'Mean milestone day':>20}")
for paths in (1, 2, 3, 4):
    each = milestone = 0
    total = 0.0
    for _ in range(RUNS):
        days = [rng.triangular(8, 12, 10) for _ in range(paths)]
        each += sum(d <= TARGET for d in days)
        milestone += max(days) <= TARGET
        total += max(days)
    print(f"{paths:>5}{each / (RUNS * paths):>19.1%}{milestone / RUNS:>19.1%}{0.5 ** paths:>8.2%}{total / RUNS:>20.2f}")

Output

Each path: 8 to 12 days, most likely 10; the milestone is due on day 10
Paths  Each path on time  Milestone on time   Exact  Mean milestone day
    1              50.3%              50.3%  50.00%               10.00
    2              50.1%              24.8%  25.00%               10.46
    3              49.8%              12.2%  12.50%               10.70
    4              50.1%               6.4%   6.25%               10.85

Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 merge.py

Each path alone was on time in about 50 % of runs; two together in 24.8 %, three in 12.2 % and four in 6.4 %, close to the exact 25, 12.5 and 6.25 %. The milestone’s mean day also slid from 10.00 to 10.85, although no single path got any longer. A single-path calculation cannot see this, and a plan with many parallel chains that all finish just in time is much later than its critical path suggests. In the fest, the chains that meet at M have a lot of float, which is why merge bias barely showed there; in a plan whose parallel chains are close in length, it dominates.

Key idea

The finish of a network is the latest of many paths, so its range is wider and later than any one path’s: simulate the whole network, and read the result as a confidence, not a single date.

Checkpoint

Check: Monte Carlo schedule risk analysis · Merge bias

  1. Question 1 of 2 The fest's Monte Carlo run with PERT weighting gives a P80 of 42.5 working days. What does that say?

    Choose one answer.

    Show the answer: Question 1 of 2

    Answer: 80 % of the simulated runs had finished by day 42.5

    In 8 of every 10 runs the fest was over by day 42.5. Committing to that date accepts a 1 in 5 chance of being late.

  2. Question 2 of 2 Three independent paths, each 70 % likely to finish on time, meet at one milestone. In what percentage of cases is the milestone on time?

    Type a number.

    Show the answer: Question 2 of 2

    Answer: 34.3 % (anything from 34.2 to 34.4 counts)

    All three must be on time: 0.7 × 0.7 × 0.7 = 0.343, so 34.3 %, although each path alone is likely to make it.

Contingency comes from the analysis, not from padding

schedule contingency: Time held before a committed finish, or before key milestones, for known risks and uncertainty, sized from a schedule risk analysis and released through change control. is time held before the committed finish for known risks and uncertainty. GAO’s guide says to size it from the risk analysis: the gap between the date at the chosen confidence, often 80 %, and the plan’s own finish. For the fest under PERT weighting that is day 43, the first whole day after the P80 of 42.5, minus day 38: 5 days. The program prints the margin for both weightings and both confidences:

Committed at PERT weighting Triangular weighting
P50 day 41, 3 days of contingency day 43, 5 days
P80 day 43, 5 days day 46, 8 days

The committed date carries that margin as one visible block before the finish, held by the project manager and released through change control, rather than as a day or two hidden in every estimate.

Communicate the result as a range with a confidence: “the fest is 80 % likely to be over by working day 43”, not “day 38” and not “day 45 to be safe”. Then re-run the analysis as actual durations arrive. The ranges of finished activities shrink to their actual values, so the range of the finish narrows, and the contingency still needed can be compared with what is left.

Ranges, seeds and the tools

Record the seed and the number of runs with every result, as the program does, so anyone can reproduce it. The PERT calculator works out three-point estimates for a list of tasks, and the probability calculator reads a normal curve for a single-path answer.

Checkpoint

Check: Schedule contingency

  1. One question A plan's deterministic finish is working day 50, and its risk analysis gives a P80 of day 56.3. Using whole days, how much contingency does an 80 % commitment need?

    Type a number.

    Show the answer: One question

    Answer: 7 days

    The first whole day after the P80 is day 57, and 57 − 50 = 7 days, the gap GAO's guide uses to size contingency.

Practise: ranges, runs and dates

The questions use the fest’s ranges and runs, a plan due on working day 50 and a data migration that drives the finish in a third of the runs. Work each number out before you answer:

Practice that adapts to you

Practise this lesson

11 questions about 5 ideas of this lesson. Each answer is explained at once, and what you get right is kept in this browser.

  1. Question 1 of 11 What are the three numbers of a three-point estimate?

    Choose one answer.

    Show the answer: Question 1 of 11

    Answer: The optimistic, the most likely and the pessimistic duration

    O, M and P record what is possible if things go well, what is most likely, and what happens if things go badly.

  2. Question 2 of 11 Signing sponsors has O = 8, M = 10 and P = 16 days. What is its mean under a triangular distribution, in days?

    Type a number.

    Show the answer: Question 2 of 11

    Answer: 11.33 days (anything from 11.32 to 11.34 counts)

    (8 + 10 + 16) ÷ 3 = 34 ÷ 3 = 11.33 days, against 10.67 with PERT weighting.

  3. Question 3 of 11 A team gives a 20-day most likely estimate but admits it has never done this kind of work. Which weighting is the more cautious choice?

    Choose one answer.

    Show the answer: Question 3 of 11

    Answer: Triangular, because it gives the extremes as much weight as the most likely value

    PERT trusts M four times as much as each extreme. If the estimators doubt their M, a triangular reading, or a wider range, is more honest, and the analysis should say which it used.

  4. Question 4 of 11 With PERT, what is the standard deviation of an activity with O = 8 and P = 16 days, in days?

    Type a number.

    Show the answer: Question 4 of 11

    Answer: 1.33 days (anything from 1.32 to 1.34 counts)

    σ = (P − O) ÷ 6 = 8 ÷ 6 = 1.33 days.

  5. Question 5 of 11 What does adding PERT means and variances along the critical path leave out?

    Choose one answer.

    Show the answer: Question 5 of 11

    Answer: The other paths, which can take over or delay the finish where they merge

    A single-path sum is a quick first answer; a Monte Carlo run of the whole network adds the effect of every other path, including merge bias.

  6. Question 6 of 11 Why does the fest's program record a seed with its Monte Carlo result?

    Choose one answer.

    Show the answer: Question 6 of 11

    Answer: So that anyone can run it again and get exactly the same numbers

    A fixed seed makes the pseudo-random draws repeatable, so a colleague, a sponsor or the next update can reproduce the analysis.

  7. Question 7 of 11 In a risk analysis, the data migration was on the critical path in 35 % of the runs, although it has 6 days of float in the plan. What should the project manager do?

    Choose one answer.

    Show the answer: Question 7 of 11

    Answer: Treat it as near-critical and manage its risks, because it drives the finish in a third of the futures

    The share of runs in which an activity is critical shows which activities can take over the finish. A third is a clear signal to manage it as closely as the critical path.

  8. Question 8 of 11 What is merge bias?

    Choose one answer.

    Show the answer: Question 8 of 11

    Answer: The extra risk where parallel paths join, because the joined event waits for the latest of them

    Even when every path is likely to be on time, the event they all feed is less likely to be, because each path is another way to be late.

  9. Question 9 of 11 In the program, the milestone's mean day rose from 10.00 with one path to 10.85 with four, although every path still took 10 days on average. Why?

    Choose one answer.

    Show the answer: Question 9 of 11

    Answer: The milestone takes the latest of the paths, and the latest of several draws is later on average than any one draw

    A maximum is pulled towards the late tail. That is why a plan full of parallel chains that each finish just in time is later than its critical path suggests.

  10. Question 10 of 11 Where does GAO's guide place schedule contingency?

    Choose one answer.

    Show the answer: Question 10 of 11

    Answer: As visible time before the committed finish, or before key milestones, held by the project manager

    Contingency is one or a few visible blocks, sized by the risk analysis and released through change control, so its use can be tracked.

  11. Question 11 of 11 How should the fest's committee state its date to the student council after the PERT-weighted analysis?

    Choose one answer.

    Show the answer: Question 11 of 11

    Answer: "80 % likely to be over by working day 43", with the plan of day 38 and the 5 days of contingency shown

    State the date with its confidence and the analysis behind it, then re-run the analysis as actual durations come in.

Interview questions

Warm-up (fresher to 2–5 years): what do P50 and P80 mean in a schedule risk analysis?

They are percentiles of the finish dates a Monte Carlo simulation produces. P50 is the date by which half of the simulated runs had finished, so the project is as likely to be later as earlier; P80 is the date by which 80 % had finished, a safer date to commit to. In the tech fest’s analysis with PERT weighting they were working days 40.4 and 42.5, against a deterministic plan of 38. The gap between the P80 and the plan’s finish is the contingency an 80 % commitment needs, here 5 days.

Two harder questions follow, about a sponsor who wants one date and about a risk analysis built on suspiciously narrow ranges. Decide what you would check first, then open each first step:

Model answers open with any pass: ₹79 for 1 week ($2.99), one payment that never renews.

  1. Mid to senior

    A schedule risk analysis of a product launch gives P50 at working day 118 and P80 at day 131, while the plan's critical path says day 110. The sponsor wants one date for the press. What do you recommend, and how do you explain it?

    Model answer, Pro. Model answers open with any pass; prices are in the notice on this page. First step and follow-ups

  2. Senior to staff

    A contractor's schedule risk analysis claims a 92 % chance of meeting your deadline. You see that every pessimistic estimate is the most likely value plus 10 %, and that no two activities are correlated. How do you judge the claim?

    Model answer, Pro. First step and follow-ups

Flashcards · 5 cards

Recall it, then check

Say the answer to yourself before you look: recalling it is what makes it stick.

  1. What three numbers make a three-point estimate, and why skew to the right?

    Optimistic (O), most likely (M) and pessimistic (P), gathered from the people who know the work (anonymously where that helps). Most schedule ranges skew right because things can go much more wrong than right.

  2. What does PERT compute for an activity?

    Expected time t_e = (O + 4M + P) / 6, standard deviation σ = (P − O) / 6. Along an independent critical path, means add and variances add (not standard deviations), so σ for the path is the square root of the summed variances.

  3. What do P50 and P80 mean, and how is contingency sized?

    P50 and P80 are the percentile dates of the Monte Carlo finish distribution: the dates by which 50 % and 80 % of simulated runs had finished. Schedule contingency is the gap between the chosen percentile (often P80) and the plan's finish, held as one visible block rather than hidden in each estimate.

  4. What is merge bias in a schedule?

    Where several paths meet, the event waits for the latest of them, so the probability of being on time multiplies. Two paths each 60 % likely to be on time are both on time only 36 % of the time. Parallel chains of similar length make a milestone later than any one of them.

  5. How should a schedule risk analysis be communicated?

    As a range with a confidence ("80 % likely to be over by working day 43"), not a single date. Record the seed and number of runs so it can be reproduced, and re-run as actual durations arrive so the finish range narrows.

Key takeaways

  • A three-point estimate records optimistic, most likely and pessimistic durations; PERT weights them (O + 4M + P) ÷ 6 and a triangular reading weights them equally, which gives later dates.
  • Adding PERT means and variances along the critical path gives a quick chance of meeting a date, but it ignores every other path.
  • A seeded Monte Carlo simulation recalculates the whole network thousands of times and reports finish dates at a confidence, such as P50 and P80.
  • Merge bias makes a milestone fed by several paths later than any one of them, so parallel chains of similar length lower the chance of finishing on time.
  • Contingency is the gap between the P80, or another chosen confidence, and the plan’s finish, held as one visible block rather than hidden in every estimate.

Terms in this lesson

merge bias
The extra risk where parallel paths join: the joined event waits for the latest path, so it is later than any one path suggests.
Monte Carlo simulation
A method that draws every uncertain input from its range many times, recalculates the model each time and reports the spread of the results.
schedule contingency
Time held before a committed finish, or before key milestones, for known risks and uncertainty, sized from a schedule risk analysis and released through change control.
schedule risk analysis
An analysis that simulates a schedule's uncertain durations and risks to give the chance of meeting each key date and the activities that most often drive the finish.
three-point estimate
An estimate given as three durations, optimistic, most likely and pessimistic, so that its range and its shape can be used in a risk analysis.