Project Management & Agile Module 4

Scheduling: networks, critical path and Gantt charts interview questions

Interview questions on “Scheduling: networks, critical path and Gantt charts”: warm-ups, then what each harder question tests and how a good answer starts.

14 questions: 5 warm-ups and 9 with model answers · Levels: Fresher to staff

Warm-up questions

Short questions with short answers, each answered in full.

  1. Fresher to mid

    What are the four types of dependency in a schedule network?

    Answered in the lesson Activities, dependencies and network diagrams

  2. Fresher to mid

    What is the difference between total float and free float?

    Total float is how long an activity can slip before the project's finish moves; free float is how long it can slip before any successor's early start moves. Free float is never larger than total float. An activity can have plenty of total float and no free float at all, when the next activity starts the moment it finishes: then any delay reaches that activity at once, although the finish has room. Total float tells the project manager which delays threaten the end date; free float tells the owners of the next activities whether a delay reaches them.

    From the lesson The critical path method, step by step

  3. Fresher to mid

    What is a schedule baseline, and why keep it once the plan has changed?

    Answered in the lesson Gantt charts, calendars and schedule baselines

  4. Fresher to mid

    What is the difference between crashing and fast-tracking?

    Both shorten a schedule, and both work only on the critical path, but they spend different things. Crashing adds resources, people, equipment or overtime, to critical activities so that they take fewer days: it costs money, and the cheapest day is found from each activity's cost slope. Fast-tracking changes the logic instead, letting activities that were planned one after the other overlap: it costs little money but adds risk, because work that starts before its predecessor finishes may have to be redone.

    From the lesson Resource levelling, crashing and fast-tracking

  5. Fresher to mid

    What do P50 and P80 mean in a schedule risk analysis?

    Answered in the lesson Three-point estimates and schedule risk analysis

Questions with model answers

What each question tests, the first step of a good answer and the follow-ups to expect.

  1. Mid to senior

    You inherit a 300-activity schedule for a hospital wing in which 90 links carry lags, several of 20 days or more, and none has a note. The finish date looks fine. What do you do before you trust it?

    What it tests
    Knowing what lags hide, telling a genuine wait from hidden work or a hidden link, and fixing the logic rather than the dates.
    First step
    Export every lagged link with its predecessor, successor and lag, sort by size, and ask the owners what happens during each wait: nothing (curing, a notice period), someone's work, or a dependency on another activity.
    Follow-ups

    From the lesson Activities, dependencies and network diagrams

    Model answer, Pro. Model answers open with any pass; prices are in the notice on this page.

    Opening the model answers with your pass…

    Model answers open with any MySmartCoPilot pass.

    • Pro pass · 1 week₹79$2.99
    • 30 days₹179$5.99
    • 1 year₹1,699$45

    One payment; a pass never renews. The price shown is the total you pay: no fees or charges are added at checkout.

    It also opens every other in-depth part in Learn and every Pro tool. Sales are final, except where the law gives you a right to withdraw, for example in the EU and the UK (refund policy).

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  2. Fresher to mid

    A product launch slipped by a week because the translated help pages were late, yet the schedule had shown the translation with 40 days of float. What most likely went wrong, and how would you have caught it?

    What it tests
    Recognising an open end or a missing successor, explaining why it produces false float, and naming the check that finds it.
    First step
    Look at the translation's successors in the schedule: if it has none, or only links that do not reach the launch milestone, its float was never real.
    Follow-ups

    From the lesson Activities, dependencies and network diagrams

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  3. Mid to senior

    A programme director asks you to mark every activity of a 120-activity schedule as critical, "so that nobody relaxes". How do you respond, and what do you offer instead?

    What it tests
    Knowing what critical means in CPM, what is lost when the word is diluted, and how to give management the focus it wants through float and near-critical paths.
    First step
    Agree with the aim, urgency, and show what the schedule loses: with everything "critical", nobody can tell which slips move the finish date. Then offer a view of the real critical path and the chains with little float.
    Follow-ups

    From the lesson The critical path method, step by step

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  4. Mid to senior

    After a contract milestone is entered as a "finish no later than" date, 40 activities in your schedule show negative float, from −3 to −15 days. Your sponsor asks whether the project is 15 days late. What do you tell them?

    What it tests
    Interpreting negative float, finding the path that really drives the milestone, and turning the numbers into options for a decision.
    First step
    Find the chain that drives the milestone, the one with −15, and check its logic and durations before reporting: negative float is only as real as the network it comes from.
    Follow-ups

    From the lesson The critical path method, step by step

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  5. Fresher to mid

    A vendor's Gantt chart for your office fit-out shows every bar finishing a week before the move-in date, and the vendor says the project is on time. What would you ask to see before you believe it?

    What it tests
    Knowing that a Gantt chart is only a view, and asking for the logic, the calendar, the baseline and the status behind it.
    First step
    Ask for the schedule file or a report of its links, not the picture: are the bars linked to each other and to move-in, and were they recalculated from actual progress at a recent status date?
    Follow-ups

    From the lesson Gantt charts, calendars and schedule baselines

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  6. Mid to senior

    A sponsor asks you to bring a 60-day office relocation in 10 working days earlier, and offers a budget for it. How do you work out what to do, and what do you tell them?

    What it tests
    Using the critical path and cost slopes to crash in the right order, considering fast-tracking and its risk, watching for new critical paths, and presenting options with their cost and risk.
    First step
    List the critical activities and the near-critical chains with less than 10 days of float, and for each critical activity its shortest duration and its cost slope.
    Follow-ups

    From the lesson Resource levelling, crashing and fast-tracking

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  7. Mid to senior

    A software release is 3 weeks late with 5 weeks of work left, and a director wants to double the team of 6 next Monday. What do you advise?

    What it tests
    Applying Brooks's law with its reasons, separating work that splits from work that does not, and offering better levers than headcount alone.
    First step
    Look at the remaining work on the critical path and ask which parts can be split among new people without much teaching, and how many days the current team would spend bringing six people up to speed.
    Follow-ups

    From the lesson Resource levelling, crashing and fast-tracking

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  8. Mid to senior

    A schedule risk analysis of a product launch gives P50 at working day 118 and P80 at day 131, while the plan's critical path says day 110. The sponsor wants one date for the press. What do you recommend, and how do you explain it?

    What it tests
    Turning a distribution into a commitment, sizing contingency from the analysis, explaining confidence in plain words, and keeping the date under control afterwards.
    First step
    Ask how costly a late announcement would be compared with an early one, because that sets the confidence the sponsor should choose; then show what each date means in those terms.
    Follow-ups

    From the lesson Three-point estimates and schedule risk analysis

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  9. Senior to staff

    A contractor's schedule risk analysis claims a 92 % chance of meeting your deadline. You see that every pessimistic estimate is the most likely value plus 10 %, and that no two activities are correlated. How do you judge the claim?

    What it tests
    Recognising anchored, narrow ranges and missing correlation, knowing their effect on the result, and asking for an analysis that can be trusted.
    First step
    Compare a few of the ranges with history: how far did similar activities actually overrun on past projects? A uniform +10 % is a sign that the ranges were derived from the plan, not estimated.
    Follow-ups

    From the lesson Three-point estimates and schedule risk analysis

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes

All Project Management & Agile interview questions · The Project Management & Agile track