Project Management & Agile  Module 5 – Cost, budgets and earned value

Cost estimates, budgets and reserves

Estimate a project three ways with honest ranges, spread the estimate into a monthly cost baseline, and size contingency and management reserve apart.

  • Intermediate
  • 10 minutes
  • Examples run with Python 3.14.8
  • By MySmartCoPilot
Free lesson, Pro answers: 10 minutes
Free: the whole lesson. With a pass: the model answers to its 2 interview questions.

What you will learn

  • Estimate a cost analogously, parametrically and bottom-up, and state each estimate as a range
  • Build a time-phased budget and cost baseline from work packages
  • Separate a contingency reserve for identified risks from a management reserve for unknowns
  • Evaluate an estimate against GAO's four characteristics of a reliable estimate

Before you start

What you’ll learn · Before you start

What you will learn

  • Estimate a cost analogously, parametrically and bottom-up, and state each estimate as a range
  • Build a time-phased budget and cost baseline from work packages
  • Separate a contingency reserve for identified risks from a management reserve for unknowns
  • Evaluate an estimate against GAO's four characteristics of a reliable estimate

Before you start

On this page

Three sound ways of estimating the same school software rollout gave 4,037, 3,899 and 3,510 thousand, a spread of 15 %, before any money had been spent. The budget needs one figure, a plan for spending it month by month and money held back for what will go wrong; get any of the three wrong and the project looks late or overspent from its first report.

You will estimate the rollout analogously, parametrically and bottom-up, each with a range, spread the chosen estimate into a monthly cost baseline, size two reserves for two kinds of uncertainty, and test the result against the four characteristics the U.S. Government Accountability Office (GAO) uses to judge an estimate.

Three estimating methods give three numbers, and each needs a range

A school group in Nagpur, 1,500 students on two campuses, wants admissions, fees, attendance and report cards on one school ERP system within six months. Before the sponsor funds it, someone has to say what it will cost. GAO’s cost guide names three common methods. An analogous estimate: An estimate that takes the actual cost of a similar past project and adjusts it for the known differences, such as size or scope; quick, but it carries the quirks of that one project. takes the cost of a similar past project and adjusts it for the differences. A parametric estimate: An estimate that applies a statistical relationship between cost and one or more drivers, fitted to comparable past projects, to the new project's values of those drivers. uses a cost estimating relationship: A formula, usually fitted to past projects, that predicts cost from a driver such as users, students or floor area; it holds only over the range of the data behind it., a statistical link between cost and a driver such as the number of students, fitted to several past projects. A bottom-up estimate: An estimate built by pricing every work package of the work breakdown structure and adding them up; GAO calls it engineering build-up. Anything left off the list costs nothing in it., which GAO calls engineering build-up, prices every work package: A lowest element of a work breakdown structure, small enough to estimate, give to one owner and check as complete. More in “Scope statements and work breakdown structures” and adds them up.

Past costs cannot be compared as they were paid. The program first moves five earlier rollouts to this year’s price base: The year whose prices an estimate is stated in. Costs from other years are moved to it with a cost index before they are compared, and inflation is added for later years. with a cost index, so Rollout A’s 1,410 from four years ago counts as 1,780, and then estimates the new rollout all three ways:

One rollout estimated three ways, each with a range Python · estimate.py
"""Estimates an invented six-month school ERP rollout (1,500 students, two campuses) three ways, each with a range.

Money is in thousands, at this year's prices. The five past rollouts are first moved to this year's price base with an
invented cost index (base year = 100), as GAO's cost guide asks before data are compared.
- Analogous: the most similar past rollout, scaled by students, plus 10 % for the second campus; the range comes from
  the cost per student of all five past rollouts.
- Parametric: a straight-line cost estimating relationship (cost = a + b x students) fitted to the five rollouts by
  least squares; the range is the largest miss of that line on its own data, applied both ways.
- Bottom-up: the sum of the work packages, each with a low, most likely and high cost.
"""

from decimal import ROUND_HALF_UP, Decimal

STUDENTS = 1500
CAMPUS_UPLIFT = Decimal("1.10")

# Past rollouts: (school, years ago, students, cost then, in thousands); index of each year, this year = 100.
PAST = [
    ("Rollout A", 4, 600, 1410),
    ("Rollout B", 3, 900, 2120),
    ("Rollout C", 2, 1100, 2460),
    ("Rollout D", 1, 1400, 3230),
    ("Rollout E", 0, 2000, 4430),
]
INDEX = {4: Decimal("79.2"), 3: Decimal("84.0"), 2: Decimal("89.0"), 1: Decimal("94.3"), 0: Decimal("100")}

# Work packages of this rollout: (name, low, most likely, high), in thousands.
PACKAGES = [
    ("Requirements and fit-gap", 300, 360, 450),
    ("Configuration and integration", 700, 810, 1050),
    ("Licences, first year", 900, 900, 990),
    ("Data migration", 240, 300, 450),
    ("Training, both campuses", 300, 360, 430),
    ("Go-live and support", 230, 270, 340),
    ("Front-office devices", 140, 150, 170),
    ("Project management", 330, 360, 400),
]


def r(x):
    return x.quantize(Decimal("1"), rounding=ROUND_HALF_UP)


base = [(name, students, Decimal(cost) * 100 / INDEX[ago]) for name, ago, students, cost in PAST]
print("Past rollouts at this year's prices (thousands):")
for name, students, cost in base:
    print(f"  {name}: {students:>5} students  {r(cost):>6}  {r(cost / students * 1000):>5} per 1,000 students")

# Analogous: the nearest rollout by size, scaled by students, plus the second campus.
nearest = min(base, key=lambda b: abs(b[1] - STUDENTS))
analogous = nearest[2] * STUDENTS / nearest[1] * CAMPUS_UPLIFT
rates = [cost / students for _, students, cost in base]
a_low, a_high = min(rates) * STUDENTS * CAMPUS_UPLIFT, max(rates) * STUDENTS * CAMPUS_UPLIFT

# Parametric: least squares on (students, cost).
n = Decimal(len(base))
mx = sum(Decimal(s) for _, s, _ in base) / n
my = sum(c for _, _, c in base) / n
b = sum((Decimal(s) - mx) * (c - my) for _, s, c in base) / sum((Decimal(s) - mx) ** 2 for _, s, _ in base)
a = my - b * mx
misses = [abs((a + b * s) - c) / c for _, s, c in base]
worst = max(misses)
parametric = (a + b * STUDENTS) * CAMPUS_UPLIFT
p_low, p_high = parametric * (1 - worst), parametric * (1 + worst)

low = sum(Decimal(p[1]) for p in PACKAGES)
likely = sum(Decimal(p[2]) for p in PACKAGES)
high = sum(Decimal(p[3]) for p in PACKAGES)

print()
print(f"Cost estimating relationship: cost = {r(a)} + {b.quantize(Decimal('0.001'))} x students "
      f"(largest miss on its own data {(worst * 100).quantize(Decimal('0.1'))} %)")
print()
print(f"{'Method':<12} {'Low':>6} {'Point':>6} {'High':>6}  Basis")
print(f"{'Analogous':<12} {r(a_low):>6} {r(analogous):>6} {r(a_high):>6}  {nearest[0]} scaled to 1,500 students, +10 % campus")
print(f"{'Parametric':<12} {r(p_low):>6} {r(parametric):>6} {r(p_high):>6}  line of five rollouts, +10 % campus")
print(f"{'Bottom-up':<12} {r(low):>6} {r(likely):>6} {r(high):>6}  sum of {len(PACKAGES)} work packages")
spread = (max(analogous, parametric, likely) - min(analogous, parametric, likely)) / likely * 100
print()
print(f"The three points differ by {spread.quantize(Decimal('0.1'))} % of the bottom-up point.")

Output

Past rollouts at this year's prices (thousands):
  Rollout A:   600 students    1780   2967 per 1,000 students
  Rollout B:   900 students    2524   2804 per 1,000 students
  Rollout C:  1100 students    2764   2513 per 1,000 students
  Rollout D:  1400 students    3425   2447 per 1,000 students
  Rollout E:  2000 students    4430   2215 per 1,000 students

Cost estimating relationship: cost = 745 + 1.866 x students (largest miss on its own data 4.8 %)

Method          Low  Point   High  Basis
Analogous      3655   4037   4896  Rollout D scaled to 1,500 students, +10 % campus
Parametric     3713   3899   4085  line of five rollouts, +10 % campus
Bottom-up      3140   3510   4280  sum of 8 work packages

The three points differ by 15.0 % of the bottom-up point.

Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 estimate.py

The analogy scales Rollout D, the nearest in size, to 1,500 students and adds 10 % for the second campus: 4,037. Its range, 3,655 to 4,896, comes from the cheapest and the dearest of the five rollouts per student, because the quirks of one project travel with an analogy. The line fitted to all five predicts 3,899 with the same uplift and misses its own data by at most 4.8 %, which gives the narrowest range; it knows only students, so a cost the driver cannot see, such as a second campus, has to be added by hand. The bottom-up sum is the lowest point, 3,510, with a range from each package’s low and high costs.

The lowest number is not automatically the best one. A bottom-up estimate prices only what is on its list, and an item left off the list costs nothing in it. That is why GAO’s best practices ask for major cost elements to be cross-checked with another method. Here the 15 % gap is the first finding: the team asks whether its packages miss something the past rollouts paid for, such as a second round of data cleaning.

Which method leads depends on what is known when the estimate is due. Answer the three questions for a project of your own:

Interactive · answer and compare Which estimating method fits your project now? Answer three questions about the project in front of you. Methods that cannot work yet are marked with the reason, and the columns that decide are highlighted.
Does the project have a work breakdown structure down to work packages?
How much cost data do you have from similar past projects?
When is the estimate due?

Answer the questions above: the table then marks what fits your case and says why the rest does not.

Three estimating methods against four things an estimate needs
Method Little defined yet Data it needs Effort to produce Detail for control
Analogous Starts from: one similar past project Good works from a one-line description and one comparable rollout Mixed one project; its quirks come along, so the range ran 3,655 to 4,896 Good hours, not weeks Poor one total; nothing to compare the work packages against later
Parametric Starts from: a cost driver and past data Good needs only the driver, here 1,500 students Poor needs several past projects on one price base to fit a line Good quick once the relationship exists Mixed a total per driver; blind to anything the driver misses, like a campus
Bottom-up Starts from: every work package Poor needs a work breakdown structure down to work packages Mixed rates and quantities per package; no history needed Poor days or weeks of work with the people who will do it Good one number per work package, the base of the budget and of earned value
How the answers decide
  • “Does the project have a work breakdown structure down to work packages?” No, only a short description: rules out Bottom-up. A bottom-up estimate adds up work packages, so it cannot exist before the work breakdown structure does.
  • “How much cost data do you have from similar past projects?” None worth using: rules out Analogous and Parametric. Both top-down methods borrow from the past; with no comparable projects there is nothing to scale or fit. With no work packages either, expert opinion, another method GAO lists, gives a first range.
  • “How much cost data do you have from similar past projects?” One close match: rules out Parametric and adds a caveat to Analogous. One project cannot show how cost moves with a driver, and an analogy from it carries its quirks, so state a wide range.
  • “When is the estimate due?” In a day or two and “Does the project have a work breakdown structure down to work packages?” Yes, the packages are known: adds a caveat to Bottom-up. A bottom-up estimate in two days skips the people who know each package; cross-check it with a top-down method.
  • “Does the project have a work breakdown structure down to work packages?” Yes, the packages are known and “When is the estimate due?” In a few weeks: adds a caveat to Analogous and Parametric. Once the packages are known, a top-down number is a cross-check, not the budget; the baseline needs one figure per package.

Early on only the top-down methods are possible, and their ranges are wide; once the work breakdown structure reaches work packages, the bottom-up estimate becomes the budget and the others become checks on it.

Putting a number into the question

Wrong: asking the data-migration lead “that comes to about 220, doesn’t it?” before the package is priced; the reply tends to land near 220 whatever the work needs. Right: ask for a low, a most likely and a high cost with no figure given, here 240, 300 and 450, and bring in the past rollouts only afterwards. An estimate that starts from a number already in the air stays biased towards it, the effect Tversky and Kahneman named anchoring.

Checkpoint

Check: Three estimating methods and their ranges

  1. Question 1 of 2 The rollout's bottom-up estimate, 3,510, is the lowest of the three points (4,037, 3,899, 3,510). What should the team do first?

    Choose one answer.

    Show the answer: Question 1 of 2

    Answer: Check the work packages for costs that the past rollouts paid for and the list leaves out

    The three methods disagree by 15 % of the bottom-up point. The bottom-up estimate becomes the budget once the work packages are known, but only after the team has asked what the past rollouts spent money on that its list omits, such as a second round of data cleaning.

  2. Question 2 of 2 A project has a signed charter but no work breakdown structure yet. The office holds the costs of six similar past projects on one price base. Which method should lead the first estimate?

    Choose one answer.

    Show the answer: Question 2 of 2

    Answer: Parametric, a relationship fitted to the six projects

    Early in a project only the top-down methods are possible. With several comparable projects on one price base, a cost estimating relationship uses them all and gives a range from its own misses; an analogy remains a useful cross-check.

A budget spreads the estimate over the months it will be spent

The sponsor releases money month by month and progress will be measured month by month, so the estimate becomes a time-phased budget: A budget with each work package's cost placed in the periods its work is planned in, so that planned spending can be compared with progress period by period.: each package’s cost placed in the months its work is planned in. The program spreads the eight packages over the six months, adds the reserve for each named risk in the month the risk could strike, and draws the running total:

The rollout's time-phased budget and its two reserves Python · budget.py
"""Turns the bottom-up estimate of the invented school ERP rollout into a time-phased budget with two reserves.

Money is in thousands, at this year's prices. Each work package is spread over the months it is planned in. The
contingency reserve is the expected cost of the identified risks (probability x cost), placed in the month each risk
could strike, and it is part of the cost baseline. The management reserve, for what nobody has identified, is 5 % of
the baseline, held outside it by the steering group. The chart draws one # for every 100 of the cumulative baseline.
"""

from decimal import ROUND_HALF_UP, Decimal

MONTHS = 6
# Work package: (name, cost, {month: share of its cost})
PACKAGES = [
    ("Requirements and fit-gap", 360, {1: "1"}),
    ("Configuration and integration", 810, {2: "0.5", 3: "0.5"}),
    ("Licences, first year", 900, {2: "1"}),
    ("Data migration", 300, {3: "0.4", 4: "0.6"}),
    ("Training, both campuses", 360, {4: "0.5", 5: "0.5"}),
    ("Go-live and support", 270, {6: "1"}),
    ("Front-office devices", 150, {4: "1"}),
    ("Project management", 360, {m: "1" for m in range(1, MONTHS + 1)}),
]
# Identified risks: (id, event, probability, cost if it happens, month it could strike)
RISKS = [
    ("R1", "data migration needs a second pass", "0.4", 200, 4),
    ("R2", "vendor raises the licence fee", "0.3", 100, 2),
    ("R3", "exam season moves training days", "0.5", 60, 5),
    ("R4", "fee-payment link slips three weeks", "0.25", 120, 3),
]
MANAGEMENT_RESERVE = Decimal("0.05")


def r(x):
    return x.quantize(Decimal("1"), rounding=ROUND_HALF_UP)


work = {m: Decimal(0) for m in range(1, MONTHS + 1)}
for name, cost, spread in PACKAGES:
    shares = {m: Decimal(s) for m, s in spread.items()}
    if name == "Project management":  # level of effort: the same amount every month
        shares = {m: Decimal(1) / MONTHS for m in shares}
    assert sum(shares.values()) == 1, name
    for m, s in shares.items():
        work[m] += cost * s

estimate = sum(work.values())
reserve = {m: Decimal(0) for m in range(1, MONTHS + 1)}
print("Contingency reserve from the risk register:")
for rid, event, p, cost, month in RISKS:
    expected = Decimal(p) * cost
    reserve[month] += expected
    print(f"  {rid} {event:<36} {p:>4} x {cost:>3} = {r(expected):>3}  (month {month})")
contingency = sum(reserve.values())
baseline = estimate + contingency
mr = baseline * MANAGEMENT_RESERVE
print()
print(f"Cost estimate (work packages)   {r(estimate):>5}")
print(f"+ contingency reserve            {r(contingency):>5}")
print(f"= cost baseline                  {r(baseline):>5}")
print(f"+ management reserve (5 %)       {r(mr):>5}  held outside the baseline")
print(f"= project budget                 {r(baseline + mr):>5}")
print()
print(f"{'Month':<6} {'Work':>5} {'Reserve':>8} {'Baseline':>9} {'Cumulative':>11}")
total = Decimal(0)
for m in range(1, MONTHS + 1):
    month = work[m] + reserve[m]
    total += month
    bar = "#" * int(total / 100)
    print(f"{m:<6} {r(work[m]):>5} {r(reserve[m]):>8} {r(month):>9} {r(total):>11}  {bar}")
print()
print(f"Half the baseline is spent by month {next(m for m in range(1, MONTHS + 1) if sum(work[k] + reserve[k] for k in range(1, m + 1)) >= baseline / 2)}.")

Output

Contingency reserve from the risk register:
  R1 data migration needs a second pass    0.4 x 200 =  80  (month 4)
  R2 vendor raises the licence fee         0.3 x 100 =  30  (month 2)
  R3 exam season moves training days       0.5 x  60 =  30  (month 5)
  R4 fee-payment link slips three weeks   0.25 x 120 =  30  (month 3)

Cost estimate (work packages)    3510
+ contingency reserve              170
= cost baseline                   3680
+ management reserve (5 %)         184  held outside the baseline
= project budget                  3864

Month   Work  Reserve  Baseline  Cumulative
1        420        0       420         420  ####
2       1365       30      1395        1815  ##################
3        585       30       615        2430  ########################
4        570       80       650        3080  ##############################
5        240       30       270        3350  #################################
6        330        0       330        3680  ####################################

Half the baseline is spent by month 3.

Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 budget.py

The cumulative column is the cost baseline: The authorised, time-phased budget that cost performance is measured against: the work packages plus the contingency reserve, without the management reserve. drawn as a curve: 420 after month 1, 1,815 after month 2 and 3,680 after month 6. Its steep second month is the first year’s licences, 900 paid at once, which is why half the baseline is spent by month 3. A finance team that reads “six months, 3,680” and expects about 613 a month would see an overrun in month 2 that is really the plan. Earned value, the next lesson, measures progress against this curve; draw it with the line graph maker to see its shape.

The same numbers stack up into the budget the sponsor sets aside. Step through them:

Interactive · stage by stage From work packages to the project budget Step through the rollout's numbers, from the eight work packages to the budget the steering group holds.
From work packages to the project budget, step 6 of 6. Showing Work packages, Contingency reserve, Cost baseline, Management reserve, Project budget. In focus: Project budget.released by decisionWork packages8 packages, 3,510Contingency reserveidentified risks, 170Cost baseline3,680, spread by monthManagement reserve5 % of baseline, 184Project budget3,864 in all

The drawing shows the whole scene; its 6 steps are listed below.

Every step as text
  1. Eight packages, one estimate. The bottom-up estimate adds the eight work packages at their most likely costs, from requirements to project management. The sum, 3,510 thousand, is the cost estimate.
  2. Risks that have names. Four risks are already in the register. Each one's probability times its cost, added up, gives a contingency reserve of 170, placed in the month each risk could strike.
  3. What progress is measured by. Work and contingency together make the cost baseline, 3,680, spread month by month. Earned value later measures progress against this curve, not against the budget.
  4. Room for what nobody named. A management reserve of 5 % of the baseline, 184, covers problems nobody has identified. It sits outside the baseline, so spending it is never hidden inside the plan.
  5. Released only by decision. When an unnamed problem appears, the steering group moves part of the reserve into the baseline, and the change is recorded like any other change to the plan.
  6. What the sponsor funds. The project budget is the baseline plus the management reserve, 3,864 thousand. Operating costs after go-live are not in it, which a life-cycle estimate must still show.

Two figures that are easily mixed up come out of it. The cost baseline, 3,680, is what performance is measured against; the project budget, 3,864, is what the sponsor funds, and the difference is the reserve nobody may spend without a decision.

Checkpoint

Check: The time-phased budget and cost baseline

  1. One question In the rollout's time-phased budget, how much of the cost baseline is planned to be spent by the end of month 2, in thousands?

    Type a number.

    A hint

    Add the baseline of month 1 and month 2, reserve included.

    Show the answer: One question

    Answer: 1815 thousand

    Month 1 holds 420 and month 2 holds 1,395 (work 1,365 plus 30 of contingency for the licence-fee risk), so the cumulative baseline is 1,815 after month 2. The first year's licences, 900, make month 2 the largest month.

Two reserves cover two kinds of uncertainty

The rollout’s 170 and 184 are not padding; they answer different questions. The contingency reserve: Budget for identified risks, usually sized as the sum of each risk's probability times its cost and held inside the cost baseline in the periods the risks could occur. pays for risks the team can name, such as a second pass of data migration: each risk’s probability times its cost, added up over the register. That sum is a pool, not a budget for each risk. If the second pass happens it costs the full 200, not the 80 it added, and the shares of the risks that pass without happening help to pay for it. The management reserve: Budget held outside the cost baseline for problems nobody has identified, released by the sponsor or steering group through a recorded decision. Some organisations, GAO among them, use the terms differently. pays for what nobody has named yet, and its size is a decision of governance, best informed by a risk analysis of the whole estimate. The table puts the two side by side, with the rollout’s figures:

Aspect Contingency reserve Management reserve
Covers identified risks in the register problems nobody has identified
Sized from probability × cost of each risk, summed: 170 a share set by governance: 5 %, 184
Where it sits inside the cost baseline, by month outside the cost baseline
Who releases it the project manager, when a named risk occurs the steering group, by a recorded decision

GAO’s earned value chapter also keeps management reserve outside the measured baseline until part of it is allocated to a problem. It reports research finding that programmes typically hold back 5 to 10 % of their contract value for it, adds that some need more and others less, and names a risk analysis of cost and schedule as one way to set the amount. The PMP examination outline lists the same two jobs under planning and managing finance: quantifying risk and contingency allocations, and managing financial reserves.

The words differ between organisations

In GAO’s guide, management reserve is the contractor’s budget for known unknowns inside the contract, and contingency is money the government office holds above it for unknown unknowns; the guide notes that other organisations may use the terms differently. What carries over is who holds each one: the reserve for known unknowns stays with the people who run the work, and the reserve for unknown unknowns is held above them by a higher authority.

Agree on the words before the first budget report, then keep the two apart in every report that follows.

Padding every package instead

Wrong: each package owner adds 20 % to be safe, so the reserve is invisible and the work expands to use it. Right: estimate each package at its most likely cost and hold the uncertainty as named reserves, so that every use of them is visible and explained.

Hidden padding also ruins later measurement: a package that finishes under its padded budget looks efficient when it was only overestimated.

Key idea

Size one reserve from the risks you can name and keep it in the plan; hold a second one outside the baseline for what nobody can name, so that spending it is always a decision.

Checkpoint

Check: Contingency and management reserve

  1. Question 1 of 2 Where does a management reserve sit, in the convention this lesson uses?

    Choose one answer.

    Show the answer: Question 1 of 2

    Answer: Outside the cost baseline, released by the steering group or sponsor

    The contingency reserve is part of the cost baseline; the management reserve is held outside it, so the baseline plus the management reserve is the project budget (3,680 + 184 = 3,864 in the rollout).

  2. Question 2 of 2 A register holds three identified risks: probability 0.2 and cost 400, probability 0.5 and cost 60, and probability 0.1 and cost 250. What contingency reserve do they give, in thousands?

    Type a number.

    A hint

    Multiply each probability by its cost, then add.

    Show the answer: Question 2 of 2

    Answer: 135 thousand

    0.2 × 400 = 80, 0.5 × 60 = 30 and 0.1 × 250 = 25, so the expected cost of the named risks is 80 + 30 + 25 = 135.

Four tests separate a reliable estimate from a guess

According to GAO’s research, a reliable estimate has four characteristics: it is comprehensive, well documented, accurate and credible. The guide’s 18 best practices and its 12-step process are there to produce them. Comprehensive means the whole life-cycle cost: The total cost of a product or system over its whole life: development, deployment, operation, support and disposal, not only the project that builds it., because a system costs money long after the project that builds it ends. The rollout’s first draft had three weaknesses planted in it, and each fails a different test:

Characteristic What GAO asks of it The draft’s weakness
Comprehensive every cost element over the whole life cycle, nothing omitted or double-counted four later years of licences, 3,600 at 900 a year, left out of the business case
Well documented sources, methods and calculations that someone else could repeat none: every figure can be traced to its source and recalculated
Accurate the best method for each element, adjusted for inflation, few mistakes past rollouts compared at the prices of their own years
Credible limits stated, major assumptions varied, a risk and uncertainty analysis the licence fee, the largest item, never varied

Two of the fixes are already in this lesson’s programs: the cost index puts every past rollout on this year’s prices, and the three methods check each other. A sensitivity check would vary the licence fee, 900 of the 3,510, and show how far the total moves. Long projects also state the price base of the estimate and the inflation they assume, because a budget in this year’s prices runs short in later years, and a cost paid in another currency names the exchange rate it was converted at; the inflation calculator shows how fast a rate compounds.

People cost more than their salaries

In India an employee’s cost to a project includes the employer’s provident fund and other statutory contributions, benefits, equipment and office space on top of salary; the employee cost calculator breaks a salary down. Budgets are usually written in rupees with lakh and crore grouping, so the rollout’s 3,864 thousand is ₹38.64 lakh.

Checkpoint

Check: GAO's four characteristics of a reliable estimate

  1. Question 1 of 2 An estimate for a new booking app covers its build and launch but none of the five years of hosting and support after it. Which of GAO's characteristics does it fail?

    Choose one answer.

    Show the answer: Question 1 of 2

    Answer: Comprehensive

    Leaving out life-cycle costs is the classic comprehensiveness failure. In the rollout, four later years of licences at 900 a year, 3,600 in all, were missing from the business case.

  2. Question 2 of 2 An analyst compares a project that cost 2,120 three years ago with a new quote of 2,400 and calls the new quote 13 % dearer, without any cost index. Which characteristic is missing?

    Choose one answer.

    Show the answer: Question 2 of 2

    Answer: Accurate, because the costs are not on one price base

    Rollout B cost 2,120 three years ago, which is 2,524 at this year's prices with the lesson's index. Compared on one price base, a quote of 2,400 is about 5 % cheaper, not 13 % dearer.

Practise: estimates, baselines and reserves

The questions reuse the rollout’s figures and add a few new cases. Work each number out before you choose an answer:

Practice that adapts to you

Practise this lesson

8 questions about 4 ideas of this lesson. Each answer is explained at once, and what you get right is kept in this browser.

  1. Question 1 of 8 Which method prices every work package and adds them up?

    Choose one answer.

    Show the answer: Question 1 of 8

    Answer: Bottom-up, which GAO calls engineering build-up

    Bottom-up estimates sum the work packages. They need the work breakdown structure and the most effort, and they give the detail a cost baseline needs.

  2. Question 2 of 8 The rollout's relationship, cost = 745 + 1.866 × students, was fitted to schools of 600 to 2,000 students. A university of 9,000 students asks for an estimate from it. What is the main problem?

    Choose one answer.

    Show the answer: Question 2 of 8

    Answer: 9,000 lies far outside the data the line was fitted to, so its 4.8 % range says nothing there

    The relationship's range came from its misses on five schools between 600 and 2,000 students. A prediction at 9,000 is an extrapolation, so it needs comparable data or another method before anyone budgets from it.

  3. Question 3 of 8 What makes a budget time-phased?

    Choose one answer.

    Show the answer: Question 3 of 8

    Answer: Each package's cost is placed in the months its work is planned in

    A time-phased budget follows the schedule: the cumulative total by month is the cost baseline, an S-shaped curve for most projects.

  4. Question 4 of 8 Finance plans the rollout at 3,680 ÷ 6, about 613 a month, and reports actual spending against that. What will its month-2 report show if everything goes exactly to plan?

    Choose one answer.

    Show the answer: Question 4 of 8

    Answer: An apparent overrun of about 780, which is really the planned licence payment

    1,395 − 613 = 782. A flat plan compares each month's spending with the wrong target, so it shows variances that are only the shape of the work.

  5. Question 5 of 8 In month 4 the data-migration risk R1 occurs, and the second pass will cost the 200 in the register. R2 and R4 passed without happening. The package owner asks the steering group to release management reserve for all of it. What do you advise?

    Choose one answer.

    Show the answer: Question 5 of 8

    Answer: Pay it from the contingency reserve first, and take only what that reserve cannot cover to the steering group

    The contingency reserve is a pool for the named risks. By month 4, R2 and R4 have passed without happening, so their 30 each joins R1's 80: 140 is there for the second pass, while R3's 30 stays for the risk still ahead in month 5. Only the remaining 60 goes to the steering group, as a request against the management reserve with the reason recorded.

  6. Question 6 of 8 A cost baseline is 2,000 thousand and the steering group holds a management reserve of 6 % of it. What is the project budget, in thousands?

    Type a number.

    Show the answer: Question 6 of 8

    Answer: 2120 thousand

    The management reserve is 0.06 × 2,000 = 120 and it sits outside the baseline, so the budget is 2,000 + 120 = 2,120.

  7. Question 7 of 8 Which of these are GAO's four characteristics of a reliable cost estimate?

    Choose every answer that is right.

    Show the answer: Question 7 of 8

    Answer:

    • Credible
    • Well documented
    • Accurate
    • Comprehensive

    GAO's cost guide groups its 18 best practices under these four characteristics and checks estimates against them.

  8. Question 8 of 8 An estimate's documentation adds: "varying the licence fee by 20 % either way moves the total by 180". Which characteristic does this line support most?

    Choose one answer.

    Show the answer: Question 8 of 8

    Answer: Credible

    0.2 × 900 = 180. A sensitivity check on the largest cost element shows the sponsor how far the total depends on one assumption, which is part of GAO's credible estimate.

Interview questions

Warm-up: how do a contingency reserve and a management reserve differ?

A contingency reserve covers risks that have been identified: it is sized from the risk register, usually as the sum of each risk’s probability times its cost, sits inside the cost baseline and is used by the project manager when one of those risks occurs. A management reserve covers problems nobody has identified: its size is set by governance, it sits outside the baseline and only the sponsor or steering group releases it, by a decision that moves budget into the baseline. In the school rollout they were 170 and 184 thousand.

Warm-up: what makes an estimate parametric?

It uses a statistical relationship between cost and one or more drivers, fitted to data from comparable past projects, and applies it to the new project’s value of the driver. The rollout’s relationship was 745 plus 1.866 for every student, fitted to five earlier rollouts on one price base. It is quick and repeatable, but it sees only its drivers.

Two harder questions follow: a sponsor who wants the budget to match a figure, and three estimates that disagree. Decide what you would check first, then open each first step:

Model answers open with any pass: ₹79 for 1 week ($2.99), one payment that never renews.

  1. Mid to senior

    Your bottom-up estimate for a clinic software rollout is 4,200 thousand with a range of 3,800 to 5,100. The sponsor says the board has already announced 3,500 and asks you to make the plan fit. What do you do?

    Model answer, Pro. Model answers open with any pass; prices are in the notice on this page. First step and follow-ups

  2. Mid to senior

    For a warehouse app, an analogy gives 2,900 thousand, a parametric model 2,750 and the bottom-up sum 2,300. The work breakdown structure is complete. Which figure goes into the budget, and what do you do about the gap?

    Model answer, Pro. First step and follow-ups

Flashcards · 5 cards

Recall it, then check

Say the answer to yourself before you look: recalling it is what makes it stick.

  1. Which three estimating methods does GAO's cost guide name?

    Analogous (adjust a similar past project's cost), parametric (a statistical cost-estimating relationship fitted to past projects), and bottom-up / engineering build-up (price every work package). Early on only the top-down methods work; later the bottom-up becomes the budget.

  2. Why is a bottom-up estimate often the lowest, and how is it checked?

    Anything missing from its package list costs nothing in it. GAO's best practices ask for major cost elements to be cross-checked with another method; a gap between methods is a first finding, not an accident.

  3. What is a time-phased budget, and what is the cost baseline?

    Each package's cost placed in the months its work is planned in. The running total is the cost baseline, drawn as a cumulative curve. It is what earned value is measured against; the sponsor's project budget sits one layer above it.

  4. What are the contingency and management reserves, and where do they sit?

    Contingency reserve covers identified risks, sized from the register (sum of probability × cost), sits INSIDE the cost baseline, released by the project manager when a named risk occurs. Management reserve covers unknown problems, sits OUTSIDE the baseline, released by the sponsor or steering group.

  5. GAO's four characteristics of a reliable estimate?

    Comprehensive (the whole life cycle, nothing omitted or double-counted), well documented (sources and calculations repeatable by someone else), accurate (best method for each element, inflation-adjusted), credible (limits stated, major assumptions varied, a risk analysis).

Key takeaways

  • Analogous, parametric and bottom-up estimates suit different stages of definition, and each should be stated as a range that comes from its own data.
  • A bottom-up estimate is often the lowest because anything missing from its list costs nothing, so major elements are cross-checked with another method.
  • A time-phased budget places each package’s cost in its months, and the cumulative curve is the cost baseline that progress is measured against.
  • A contingency reserve for named risks is one pool inside the baseline, while a management reserve for unknowns sits outside it and is released only by a decision.
  • GAO judges an estimate reliable when it is comprehensive, well documented, accurate and credible, which includes the whole life cycle, one price base and a test of its major assumptions.

Terms in this lesson

analogous estimate
An estimate that takes the actual cost of a similar past project and adjusts it for the known differences, such as size or scope; quick, but it carries the quirks of that one project.
bottom-up estimate
An estimate built by pricing every work package of the work breakdown structure and adding them up; GAO calls it engineering build-up. Anything left off the list costs nothing in it.
contingency reserve
Budget for identified risks, usually sized as the sum of each risk's probability times its cost and held inside the cost baseline in the periods the risks could occur.
cost baseline
The authorised, time-phased budget that cost performance is measured against: the work packages plus the contingency reserve, without the management reserve.
cost estimating relationship
A formula, usually fitted to past projects, that predicts cost from a driver such as users, students or floor area; it holds only over the range of the data behind it.
life-cycle cost
The total cost of a product or system over its whole life: development, deployment, operation, support and disposal, not only the project that builds it.
management reserve
Budget held outside the cost baseline for problems nobody has identified, released by the sponsor or steering group through a recorded decision. Some organisations, GAO among them, use the terms differently.
parametric estimate
An estimate that applies a statistical relationship between cost and one or more drivers, fitted to comparable past projects, to the new project's values of those drivers.
price base
The year whose prices an estimate is stated in. Costs from other years are moved to it with a cost index before they are compared, and inflation is added for later years.
time-phased budget
A budget with each work package's cost placed in the periods its work is planned in, so that planned spending can be compared with progress period by period.

References