Project Management & Agile Module 5 – Cost, budgets and earned value
Cost estimates, budgets and reserves
Estimate a project three ways with honest ranges, spread the estimate into a monthly cost baseline, and size contingency and management reserve apart.
What you will learn
- Estimate a cost analogously, parametrically and bottom-up, and state each estimate as a range
- Build a time-phased budget and cost baseline from work packages
- Separate a contingency reserve for identified risks from a management reserve for unknowns
- Evaluate an estimate against GAO's four characteristics of a reliable estimate
Before you start
What you’ll learn · Before you start
What you will learn
- Estimate a cost analogously, parametrically and bottom-up, and state each estimate as a range
- Build a time-phased budget and cost baseline from work packages
- Separate a contingency reserve for identified risks from a management reserve for unknowns
- Evaluate an estimate against GAO's four characteristics of a reliable estimate
Before you start
On this page
Three sound ways of estimating the same school software rollout gave 4,037, 3,899 and 3,510 thousand, a spread of 15 %, before any money had been spent. The budget needs one figure, a plan for spending it month by month and money held back for what will go wrong; get any of the three wrong and the project looks late or overspent from its first report.
You will estimate the rollout analogously, parametrically and bottom-up, each with a range, spread the chosen estimate into a monthly cost baseline, size two reserves for two kinds of uncertainty, and test the result against the four characteristics the U.S. Government Accountability Office (GAO) uses to judge an estimate.
Three estimating methods give three numbers, and each needs a range
A school group in Nagpur, 1,500 students on two campuses, wants admissions, fees, attendance and report cards on one school ERP system within six months. Before the sponsor funds it, someone has to say what it will cost. GAO’s cost guide names three common methods. An analogous estimate: An estimate that takes the actual cost of a similar past project and adjusts it for the known differences, such as size or scope; quick, but it carries the quirks of that one project. takes the cost of a similar past project and adjusts it for the differences. A parametric estimate: An estimate that applies a statistical relationship between cost and one or more drivers, fitted to comparable past projects, to the new project's values of those drivers. uses a cost estimating relationship: A formula, usually fitted to past projects, that predicts cost from a driver such as users, students or floor area; it holds only over the range of the data behind it., a statistical link between cost and a driver such as the number of students, fitted to several past projects. A bottom-up estimate: An estimate built by pricing every work package of the work breakdown structure and adding them up; GAO calls it engineering build-up. Anything left off the list costs nothing in it., which GAO calls engineering build-up, prices every work package: A lowest element of a work breakdown structure, small enough to estimate, give to one owner and check as complete. More in “Scope statements and work breakdown structures” and adds them up.
Past costs cannot be compared as they were paid. The program first moves five earlier rollouts to this year’s price base: The year whose prices an estimate is stated in. Costs from other years are moved to it with a cost index before they are compared, and inflation is added for later years. with a cost index, so Rollout A’s 1,410 from four years ago counts as 1,780, and then estimates the new rollout all three ways:
"""Estimates an invented six-month school ERP rollout (1,500 students, two campuses) three ways, each with a range.
Money is in thousands, at this year's prices. The five past rollouts are first moved to this year's price base with an
invented cost index (base year = 100), as GAO's cost guide asks before data are compared.
- Analogous: the most similar past rollout, scaled by students, plus 10 % for the second campus; the range comes from
the cost per student of all five past rollouts.
- Parametric: a straight-line cost estimating relationship (cost = a + b x students) fitted to the five rollouts by
least squares; the range is the largest miss of that line on its own data, applied both ways.
- Bottom-up: the sum of the work packages, each with a low, most likely and high cost.
"""
from decimal import ROUND_HALF_UP, Decimal
STUDENTS = 1500
CAMPUS_UPLIFT = Decimal("1.10")
# Past rollouts: (school, years ago, students, cost then, in thousands); index of each year, this year = 100.
PAST = [
("Rollout A", 4, 600, 1410),
("Rollout B", 3, 900, 2120),
("Rollout C", 2, 1100, 2460),
("Rollout D", 1, 1400, 3230),
("Rollout E", 0, 2000, 4430),
]
INDEX = {4: Decimal("79.2"), 3: Decimal("84.0"), 2: Decimal("89.0"), 1: Decimal("94.3"), 0: Decimal("100")}
# Work packages of this rollout: (name, low, most likely, high), in thousands.
PACKAGES = [
("Requirements and fit-gap", 300, 360, 450),
("Configuration and integration", 700, 810, 1050),
("Licences, first year", 900, 900, 990),
("Data migration", 240, 300, 450),
("Training, both campuses", 300, 360, 430),
("Go-live and support", 230, 270, 340),
("Front-office devices", 140, 150, 170),
("Project management", 330, 360, 400),
]
def r(x):
return x.quantize(Decimal("1"), rounding=ROUND_HALF_UP)
base = [(name, students, Decimal(cost) * 100 / INDEX[ago]) for name, ago, students, cost in PAST]
print("Past rollouts at this year's prices (thousands):")
for name, students, cost in base:
print(f" {name}: {students:>5} students {r(cost):>6} {r(cost / students * 1000):>5} per 1,000 students")
# Analogous: the nearest rollout by size, scaled by students, plus the second campus.
nearest = min(base, key=lambda b: abs(b[1] - STUDENTS))
analogous = nearest[2] * STUDENTS / nearest[1] * CAMPUS_UPLIFT
rates = [cost / students for _, students, cost in base]
a_low, a_high = min(rates) * STUDENTS * CAMPUS_UPLIFT, max(rates) * STUDENTS * CAMPUS_UPLIFT
# Parametric: least squares on (students, cost).
n = Decimal(len(base))
mx = sum(Decimal(s) for _, s, _ in base) / n
my = sum(c for _, _, c in base) / n
b = sum((Decimal(s) - mx) * (c - my) for _, s, c in base) / sum((Decimal(s) - mx) ** 2 for _, s, _ in base)
a = my - b * mx
misses = [abs((a + b * s) - c) / c for _, s, c in base]
worst = max(misses)
parametric = (a + b * STUDENTS) * CAMPUS_UPLIFT
p_low, p_high = parametric * (1 - worst), parametric * (1 + worst)
low = sum(Decimal(p[1]) for p in PACKAGES)
likely = sum(Decimal(p[2]) for p in PACKAGES)
high = sum(Decimal(p[3]) for p in PACKAGES)
print()
print(f"Cost estimating relationship: cost = {r(a)} + {b.quantize(Decimal('0.001'))} x students "
f"(largest miss on its own data {(worst * 100).quantize(Decimal('0.1'))} %)")
print()
print(f"{'Method':<12} {'Low':>6} {'Point':>6} {'High':>6} Basis")
print(f"{'Analogous':<12} {r(a_low):>6} {r(analogous):>6} {r(a_high):>6} {nearest[0]} scaled to 1,500 students, +10 % campus")
print(f"{'Parametric':<12} {r(p_low):>6} {r(parametric):>6} {r(p_high):>6} line of five rollouts, +10 % campus")
print(f"{'Bottom-up':<12} {r(low):>6} {r(likely):>6} {r(high):>6} sum of {len(PACKAGES)} work packages")
spread = (max(analogous, parametric, likely) - min(analogous, parametric, likely)) / likely * 100
print()
print(f"The three points differ by {spread.quantize(Decimal('0.1'))} % of the bottom-up point.") Output
Past rollouts at this year's prices (thousands): Rollout A: 600 students 1780 2967 per 1,000 students Rollout B: 900 students 2524 2804 per 1,000 students Rollout C: 1100 students 2764 2513 per 1,000 students Rollout D: 1400 students 3425 2447 per 1,000 students Rollout E: 2000 students 4430 2215 per 1,000 students Cost estimating relationship: cost = 745 + 1.866 x students (largest miss on its own data 4.8 %) Method Low Point High Basis Analogous 3655 4037 4896 Rollout D scaled to 1,500 students, +10 % campus Parametric 3713 3899 4085 line of five rollouts, +10 % campus Bottom-up 3140 3510 4280 sum of 8 work packages The three points differ by 15.0 % of the bottom-up point.
Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 estimate.py
The analogy scales Rollout D, the nearest in size, to 1,500 students and adds 10 % for the second campus: 4,037. Its range, 3,655 to 4,896, comes from the cheapest and the dearest of the five rollouts per student, because the quirks of one project travel with an analogy. The line fitted to all five predicts 3,899 with the same uplift and misses its own data by at most 4.8 %, which gives the narrowest range; it knows only students, so a cost the driver cannot see, such as a second campus, has to be added by hand. The bottom-up sum is the lowest point, 3,510, with a range from each package’s low and high costs.
The lowest number is not automatically the best one. A bottom-up estimate prices only what is on its list, and an item left off the list costs nothing in it. That is why GAO’s best practices ask for major cost elements to be cross-checked with another method. Here the 15 % gap is the first finding: the team asks whether its packages miss something the past rollouts paid for, such as a second round of data cleaning.
Which method leads depends on what is known when the estimate is due. Answer the three questions for a project of your own:
Answer the questions above: the table then marks what fits your case and says why the rest does not.
| Method | Little defined yet | Data it needs | Effort to produce | Detail for control |
|---|---|---|---|---|
| Analogous Starts from: one similar past project | Good works from a one-line description and one comparable rollout | Mixed one project; its quirks come along, so the range ran 3,655 to 4,896 | Good hours, not weeks | Poor one total; nothing to compare the work packages against later |
| Parametric Starts from: a cost driver and past data | Good needs only the driver, here 1,500 students | Poor needs several past projects on one price base to fit a line | Good quick once the relationship exists | Mixed a total per driver; blind to anything the driver misses, like a campus |
| Bottom-up Starts from: every work package | Poor needs a work breakdown structure down to work packages | Mixed rates and quantities per package; no history needed | Poor days or weeks of work with the people who will do it | Good one number per work package, the base of the budget and of earned value |
How the answers decide
- “Does the project have a work breakdown structure down to work packages?” No, only a short description: rules out Bottom-up. A bottom-up estimate adds up work packages, so it cannot exist before the work breakdown structure does.
- “How much cost data do you have from similar past projects?” None worth using: rules out Analogous and Parametric. Both top-down methods borrow from the past; with no comparable projects there is nothing to scale or fit. With no work packages either, expert opinion, another method GAO lists, gives a first range.
- “How much cost data do you have from similar past projects?” One close match: rules out Parametric and adds a caveat to Analogous. One project cannot show how cost moves with a driver, and an analogy from it carries its quirks, so state a wide range.
- “When is the estimate due?” In a day or two and “Does the project have a work breakdown structure down to work packages?” Yes, the packages are known: adds a caveat to Bottom-up. A bottom-up estimate in two days skips the people who know each package; cross-check it with a top-down method.
- “Does the project have a work breakdown structure down to work packages?” Yes, the packages are known and “When is the estimate due?” In a few weeks: adds a caveat to Analogous and Parametric. Once the packages are known, a top-down number is a cross-check, not the budget; the baseline needs one figure per package.
Early on only the top-down methods are possible, and their ranges are wide; once the work breakdown structure reaches work packages, the bottom-up estimate becomes the budget and the others become checks on it.
Putting a number into the question
Wrong: asking the data-migration lead “that comes to about 220, doesn’t it?” before the package is priced; the reply tends to land near 220 whatever the work needs. Right: ask for a low, a most likely and a high cost with no figure given, here 240, 300 and 450, and bring in the past rollouts only afterwards. An estimate that starts from a number already in the air stays biased towards it, the effect Tversky and Kahneman named anchoring.
Checkpoint
Check: Three estimating methods and their ranges
A budget spreads the estimate over the months it will be spent
The sponsor releases money month by month and progress will be measured month by month, so the estimate becomes a time-phased budget: A budget with each work package's cost placed in the periods its work is planned in, so that planned spending can be compared with progress period by period.: each package’s cost placed in the months its work is planned in. The program spreads the eight packages over the six months, adds the reserve for each named risk in the month the risk could strike, and draws the running total:
"""Turns the bottom-up estimate of the invented school ERP rollout into a time-phased budget with two reserves.
Money is in thousands, at this year's prices. Each work package is spread over the months it is planned in. The
contingency reserve is the expected cost of the identified risks (probability x cost), placed in the month each risk
could strike, and it is part of the cost baseline. The management reserve, for what nobody has identified, is 5 % of
the baseline, held outside it by the steering group. The chart draws one # for every 100 of the cumulative baseline.
"""
from decimal import ROUND_HALF_UP, Decimal
MONTHS = 6
# Work package: (name, cost, {month: share of its cost})
PACKAGES = [
("Requirements and fit-gap", 360, {1: "1"}),
("Configuration and integration", 810, {2: "0.5", 3: "0.5"}),
("Licences, first year", 900, {2: "1"}),
("Data migration", 300, {3: "0.4", 4: "0.6"}),
("Training, both campuses", 360, {4: "0.5", 5: "0.5"}),
("Go-live and support", 270, {6: "1"}),
("Front-office devices", 150, {4: "1"}),
("Project management", 360, {m: "1" for m in range(1, MONTHS + 1)}),
]
# Identified risks: (id, event, probability, cost if it happens, month it could strike)
RISKS = [
("R1", "data migration needs a second pass", "0.4", 200, 4),
("R2", "vendor raises the licence fee", "0.3", 100, 2),
("R3", "exam season moves training days", "0.5", 60, 5),
("R4", "fee-payment link slips three weeks", "0.25", 120, 3),
]
MANAGEMENT_RESERVE = Decimal("0.05")
def r(x):
return x.quantize(Decimal("1"), rounding=ROUND_HALF_UP)
work = {m: Decimal(0) for m in range(1, MONTHS + 1)}
for name, cost, spread in PACKAGES:
shares = {m: Decimal(s) for m, s in spread.items()}
if name == "Project management": # level of effort: the same amount every month
shares = {m: Decimal(1) / MONTHS for m in shares}
assert sum(shares.values()) == 1, name
for m, s in shares.items():
work[m] += cost * s
estimate = sum(work.values())
reserve = {m: Decimal(0) for m in range(1, MONTHS + 1)}
print("Contingency reserve from the risk register:")
for rid, event, p, cost, month in RISKS:
expected = Decimal(p) * cost
reserve[month] += expected
print(f" {rid} {event:<36} {p:>4} x {cost:>3} = {r(expected):>3} (month {month})")
contingency = sum(reserve.values())
baseline = estimate + contingency
mr = baseline * MANAGEMENT_RESERVE
print()
print(f"Cost estimate (work packages) {r(estimate):>5}")
print(f"+ contingency reserve {r(contingency):>5}")
print(f"= cost baseline {r(baseline):>5}")
print(f"+ management reserve (5 %) {r(mr):>5} held outside the baseline")
print(f"= project budget {r(baseline + mr):>5}")
print()
print(f"{'Month':<6} {'Work':>5} {'Reserve':>8} {'Baseline':>9} {'Cumulative':>11}")
total = Decimal(0)
for m in range(1, MONTHS + 1):
month = work[m] + reserve[m]
total += month
bar = "#" * int(total / 100)
print(f"{m:<6} {r(work[m]):>5} {r(reserve[m]):>8} {r(month):>9} {r(total):>11} {bar}")
print()
print(f"Half the baseline is spent by month {next(m for m in range(1, MONTHS + 1) if sum(work[k] + reserve[k] for k in range(1, m + 1)) >= baseline / 2)}.") Output
Contingency reserve from the risk register: R1 data migration needs a second pass 0.4 x 200 = 80 (month 4) R2 vendor raises the licence fee 0.3 x 100 = 30 (month 2) R3 exam season moves training days 0.5 x 60 = 30 (month 5) R4 fee-payment link slips three weeks 0.25 x 120 = 30 (month 3) Cost estimate (work packages) 3510 + contingency reserve 170 = cost baseline 3680 + management reserve (5 %) 184 held outside the baseline = project budget 3864 Month Work Reserve Baseline Cumulative 1 420 0 420 420 #### 2 1365 30 1395 1815 ################## 3 585 30 615 2430 ######################## 4 570 80 650 3080 ############################## 5 240 30 270 3350 ################################# 6 330 0 330 3680 #################################### Half the baseline is spent by month 3.
Recorded with Python 3.14.8 on macOS 26 arm64. To run it yourself: mise exec python@3.14.8 -- python3 budget.py
The cumulative column is the cost baseline: The authorised, time-phased budget that cost performance is measured against: the work packages plus the contingency reserve, without the management reserve. drawn as a curve: 420 after month 1, 1,815 after month 2 and 3,680 after month 6. Its steep second month is the first year’s licences, 900 paid at once, which is why half the baseline is spent by month 3. A finance team that reads “six months, 3,680” and expects about 613 a month would see an overrun in month 2 that is really the plan. Earned value, the next lesson, measures progress against this curve; draw it with the line graph maker to see its shape.
The same numbers stack up into the budget the sponsor sets aside. Step through them:
The drawing shows the whole scene; its 6 steps are listed below.
Every step as text
- Eight packages, one estimate. The bottom-up estimate adds the eight work packages at their most likely costs, from requirements to project management. The sum, 3,510 thousand, is the cost estimate.
- Risks that have names. Four risks are already in the register. Each one's probability times its cost, added up, gives a contingency reserve of 170, placed in the month each risk could strike.
- What progress is measured by. Work and contingency together make the cost baseline, 3,680, spread month by month. Earned value later measures progress against this curve, not against the budget.
- Room for what nobody named. A management reserve of 5 % of the baseline, 184, covers problems nobody has identified. It sits outside the baseline, so spending it is never hidden inside the plan.
- Released only by decision. When an unnamed problem appears, the steering group moves part of the reserve into the baseline, and the change is recorded like any other change to the plan.
- What the sponsor funds. The project budget is the baseline plus the management reserve, 3,864 thousand. Operating costs after go-live are not in it, which a life-cycle estimate must still show.
Two figures that are easily mixed up come out of it. The cost baseline, 3,680, is what performance is measured against; the project budget, 3,864, is what the sponsor funds, and the difference is the reserve nobody may spend without a decision.
Checkpoint
Check: The time-phased budget and cost baseline
Two reserves cover two kinds of uncertainty
The rollout’s 170 and 184 are not padding; they answer different questions. The contingency reserve: Budget for identified risks, usually sized as the sum of each risk's probability times its cost and held inside the cost baseline in the periods the risks could occur. pays for risks the team can name, such as a second pass of data migration: each risk’s probability times its cost, added up over the register. That sum is a pool, not a budget for each risk. If the second pass happens it costs the full 200, not the 80 it added, and the shares of the risks that pass without happening help to pay for it. The management reserve: Budget held outside the cost baseline for problems nobody has identified, released by the sponsor or steering group through a recorded decision. Some organisations, GAO among them, use the terms differently. pays for what nobody has named yet, and its size is a decision of governance, best informed by a risk analysis of the whole estimate. The table puts the two side by side, with the rollout’s figures:
| Aspect | Contingency reserve | Management reserve |
|---|---|---|
| Covers | identified risks in the register | problems nobody has identified |
| Sized from | probability × cost of each risk, summed: 170 | a share set by governance: 5 %, 184 |
| Where it sits | inside the cost baseline, by month | outside the cost baseline |
| Who releases it | the project manager, when a named risk occurs | the steering group, by a recorded decision |
GAO’s earned value chapter also keeps management reserve outside the measured baseline until part of it is allocated to a problem. It reports research finding that programmes typically hold back 5 to 10 % of their contract value for it, adds that some need more and others less, and names a risk analysis of cost and schedule as one way to set the amount. The PMP examination outline lists the same two jobs under planning and managing finance: quantifying risk and contingency allocations, and managing financial reserves.
The words differ between organisations
In GAO’s guide, management reserve is the contractor’s budget for known unknowns inside the contract, and contingency is money the government office holds above it for unknown unknowns; the guide notes that other organisations may use the terms differently. What carries over is who holds each one: the reserve for known unknowns stays with the people who run the work, and the reserve for unknown unknowns is held above them by a higher authority.
Agree on the words before the first budget report, then keep the two apart in every report that follows.
Padding every package instead
Wrong: each package owner adds 20 % to be safe, so the reserve is invisible and the work expands to use it. Right: estimate each package at its most likely cost and hold the uncertainty as named reserves, so that every use of them is visible and explained.
Hidden padding also ruins later measurement: a package that finishes under its padded budget looks efficient when it was only overestimated.
Key idea
Size one reserve from the risks you can name and keep it in the plan; hold a second one outside the baseline for what nobody can name, so that spending it is always a decision.
Checkpoint
Check: Contingency and management reserve
Four tests separate a reliable estimate from a guess
According to GAO’s research, a reliable estimate has four characteristics: it is comprehensive, well documented, accurate and credible. The guide’s 18 best practices and its 12-step process are there to produce them. Comprehensive means the whole life-cycle cost: The total cost of a product or system over its whole life: development, deployment, operation, support and disposal, not only the project that builds it., because a system costs money long after the project that builds it ends. The rollout’s first draft had three weaknesses planted in it, and each fails a different test:
| Characteristic | What GAO asks of it | The draft’s weakness |
|---|---|---|
| Comprehensive | every cost element over the whole life cycle, nothing omitted or double-counted | four later years of licences, 3,600 at 900 a year, left out of the business case |
| Well documented | sources, methods and calculations that someone else could repeat | none: every figure can be traced to its source and recalculated |
| Accurate | the best method for each element, adjusted for inflation, few mistakes | past rollouts compared at the prices of their own years |
| Credible | limits stated, major assumptions varied, a risk and uncertainty analysis | the licence fee, the largest item, never varied |
Two of the fixes are already in this lesson’s programs: the cost index puts every past rollout on this year’s prices, and the three methods check each other. A sensitivity check would vary the licence fee, 900 of the 3,510, and show how far the total moves. Long projects also state the price base of the estimate and the inflation they assume, because a budget in this year’s prices runs short in later years, and a cost paid in another currency names the exchange rate it was converted at; the inflation calculator shows how fast a rate compounds.
People cost more than their salaries
In India an employee’s cost to a project includes the employer’s provident fund and other statutory contributions, benefits, equipment and office space on top of salary; the employee cost calculator breaks a salary down. Budgets are usually written in rupees with lakh and crore grouping, so the rollout’s 3,864 thousand is ₹38.64 lakh.
Checkpoint
Check: GAO's four characteristics of a reliable estimate
Practise: estimates, baselines and reserves
The questions reuse the rollout’s figures and add a few new cases. Work each number out before you choose an answer:
Practice that adapts to you
Practise this lesson
8 questions about 4 ideas of this lesson. Each answer is explained at once, and what you get right is kept in this browser.
Interview questions
Warm-up: how do a contingency reserve and a management reserve differ?
A contingency reserve covers risks that have been identified: it is sized from the risk register, usually as the sum of each risk’s probability times its cost, sits inside the cost baseline and is used by the project manager when one of those risks occurs. A management reserve covers problems nobody has identified: its size is set by governance, it sits outside the baseline and only the sponsor or steering group releases it, by a decision that moves budget into the baseline. In the school rollout they were 170 and 184 thousand.
Warm-up: what makes an estimate parametric?
It uses a statistical relationship between cost and one or more drivers, fitted to data from comparable past projects, and applies it to the new project’s value of the driver. The rollout’s relationship was 745 plus 1.866 for every student, fitted to five earlier rollouts on one price base. It is quick and repeatable, but it sees only its drivers.
Two harder questions follow: a sponsor who wants the budget to match a figure, and three estimates that disagree. Decide what you would check first, then open each first step:
Model answers open with any pass: ₹79 for 1 week ($2.99), one payment that never renews.
-
Mid to senior
Your bottom-up estimate for a clinic software rollout is 4,200 thousand with a range of 3,800 to 5,100. The sponsor says the board has already announced 3,500 and asks you to make the plan fit. What do you do?
-
Mid to senior
For a warehouse app, an analogy gives 2,900 thousand, a parametric model 2,750 and the bottom-up sum 2,300. The work breakdown structure is complete. Which figure goes into the budget, and what do you do about the gap?
Flashcards · 5 cards
Recall it, then check
Say the answer to yourself before you look: recalling it is what makes it stick.
-
Which three estimating methods does GAO's cost guide name?
Analogous (adjust a similar past project's cost), parametric (a statistical cost-estimating relationship fitted to past projects), and bottom-up / engineering build-up (price every work package). Early on only the top-down methods work; later the bottom-up becomes the budget.
-
Why is a bottom-up estimate often the lowest, and how is it checked?
Anything missing from its package list costs nothing in it. GAO's best practices ask for major cost elements to be cross-checked with another method; a gap between methods is a first finding, not an accident.
-
What is a time-phased budget, and what is the cost baseline?
Each package's cost placed in the months its work is planned in. The running total is the cost baseline, drawn as a cumulative curve. It is what earned value is measured against; the sponsor's project budget sits one layer above it.
-
What are the contingency and management reserves, and where do they sit?
Contingency reserve covers identified risks, sized from the register (sum of probability × cost), sits INSIDE the cost baseline, released by the project manager when a named risk occurs. Management reserve covers unknown problems, sits OUTSIDE the baseline, released by the sponsor or steering group.
-
GAO's four characteristics of a reliable estimate?
Comprehensive (the whole life cycle, nothing omitted or double-counted), well documented (sources and calculations repeatable by someone else), accurate (best method for each element, inflation-adjusted), credible (limits stated, major assumptions varied, a risk analysis).
Key takeaways
- Analogous, parametric and bottom-up estimates suit different stages of definition, and each should be stated as a range that comes from its own data.
- A bottom-up estimate is often the lowest because anything missing from its list costs nothing, so major elements are cross-checked with another method.
- A time-phased budget places each package’s cost in its months, and the cumulative curve is the cost baseline that progress is measured against.
- A contingency reserve for named risks is one pool inside the baseline, while a management reserve for unknowns sits outside it and is released only by a decision.
- GAO judges an estimate reliable when it is comprehensive, well documented, accurate and credible, which includes the whole life cycle, one price base and a test of its major assumptions.
Terms in this lesson
- analogous estimate
- An estimate that takes the actual cost of a similar past project and adjusts it for the known differences, such as size or scope; quick, but it carries the quirks of that one project.
- bottom-up estimate
- An estimate built by pricing every work package of the work breakdown structure and adding them up; GAO calls it engineering build-up. Anything left off the list costs nothing in it.
- contingency reserve
- Budget for identified risks, usually sized as the sum of each risk's probability times its cost and held inside the cost baseline in the periods the risks could occur.
- cost baseline
- The authorised, time-phased budget that cost performance is measured against: the work packages plus the contingency reserve, without the management reserve.
- cost estimating relationship
- A formula, usually fitted to past projects, that predicts cost from a driver such as users, students or floor area; it holds only over the range of the data behind it.
- life-cycle cost
- The total cost of a product or system over its whole life: development, deployment, operation, support and disposal, not only the project that builds it.
- management reserve
- Budget held outside the cost baseline for problems nobody has identified, released by the sponsor or steering group through a recorded decision. Some organisations, GAO among them, use the terms differently.
- parametric estimate
- An estimate that applies a statistical relationship between cost and one or more drivers, fitted to comparable past projects, to the new project's values of those drivers.
- price base
- The year whose prices an estimate is stated in. Costs from other years are moved to it with a cost index before they are compared, and inflation is added for later years.
- time-phased budget
- A budget with each work package's cost placed in the periods its work is planned in, so that planned spending can be compared with progress period by period.
References
- Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs (GAO-20-195G) (U.S. Government Accountability Office)
- Project Management Professional (PMP) Examination Content Outline (2026 edition) (Project Management Institute)
- decimal: decimal fixed-point and floating-point arithmetic (Python 3.14 standard library) (Python Software Foundation)
- Judgment under Uncertainty: Heuristics and Biases (Science 185(4157), 1974) (American Association for the Advancement of Science)