Project Management & Agile Module 2

Initiating: business case, charter and stakeholders interview questions

Interview questions on “Initiating: business case, charter and stakeholders”: warm-ups, then what each harder question tests and how a good answer starts.

12 questions: 4 warm-ups and 8 with model answers · Levels: Fresher to staff

Warm-up questions

Short questions with short answers, each answered in full.

  1. Fresher to mid

    How do NPV and payback differ?

    Answered in the lesson Business cases and choosing between projects

  2. Fresher to mid

    What separates an assumption from a constraint in a charter?

    Answered in the lesson Writing a project charter with clear objectives

  3. Fresher to mid

    What does a power-interest grid tell you, and what does it leave out?

    Answered in the lesson Identifying and analysing stakeholders

  4. Fresher to mid

    How do responsible and accountable differ in a RACI chart?

    Answered in the lesson RACI charts, decision rights and escalation

Questions with model answers

What each question tests, the first step of a good answer and the follow-ups to expect.

  1. Mid to senior

    Two options exclude each other. Option A costs 150 and has an IRR of 68 %; option B costs 900 and has an IRR of 25 % but the higher NPV at your 10 % required rate. The sponsor wants A "because it has the best return". How do you respond?

    What it tests
    Knowing that IRR ignores scale, that NPV at the required rate decides between options that exclude each other, and explaining it to a sponsor with the numbers.
    First step
    Agree on the goal first: the most value for the organisation at the rate it requires. Then show both NPVs side by side, because IRR says how fast money grows, not how much value an option adds in total.
    Follow-ups

    From the lesson Business cases and choosing between projects

    Model answer, Pro. Model answers open with any pass; prices are in the notice on this page.

    Opening the model answers with your pass…

    Model answers open with any MySmartCoPilot pass.

    • Pro pass · 1 week₹79$2.99
    • 30 days₹179$5.99
    • 1 year₹1,699$45

    One payment; a pass never renews. The price shown is the total you pay: no fees or charges are added at checkout.

    It also opens every other in-depth part in Learn and every Pro tool. Sales are final, except where the law gives you a right to withdraw, for example in the EU and the UK (refund policy).

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  2. Senior to staff

    A project has spent 8 million of its 10 million budget, its revised estimate to finish is 6 million more, and its benefits have fallen because a competitor launched first. The steering group says it must finish because so much is spent. What do you advise?

    What it tests
    Applying the sunk-cost principle, comparing only the costs and benefits still ahead, and presenting stop, change or continue as options with numbers.
    First step
    Set the 8 already spent aside, because no choice brings it back. Compare the 6 still needed with the benefits that finishing would still bring, and lay out the options: finish, cut scope, pivot or stop.
    Follow-ups

    From the lesson Business cases and choosing between projects

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  3. Mid to senior

    You are drafting a charter for a 4 million project. You learn that the director named as sponsor can authorise only 1 million; the rest needs the commissioner. The director says to start anyway and sort out the money later. What do you do?

    What it tests
    Knowing that a charter's authority comes from someone who controls the money, and fixing the sponsorship before work starts without losing the director's support.
    First step
    Thank the director, then point out the gap plainly: work started on authority nobody holds can be stopped at any moment, and people's time spent on it is lost. Offer two routes: the commissioner becomes the sponsor with the director as the day-to-day lead, or the charter is cut to a first phase that fits within 1 million.
    Follow-ups

    From the lesson Writing a project charter with clear objectives

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 3 minutes
  4. Mid to senior

    A sponsor's only objective for a new staff portal is "make HR easier". When you suggest targets, the sponsor says numbers will box the team in. How do you turn this into objectives the project can be judged by?

    What it tests
    Turning a vague goal into objectives with a target, a deadline and a source, and handling a sponsor's worry about being held to numbers.
    First step
    Ask what "easier" would look like to the people involved: fewer forms, faster answers, fewer calls to HR. Find where those things are already counted today, and propose two or three objectives built on those counts, framed as the sponsor's own intent made visible rather than as a trap.
    Follow-ups

    From the lesson Writing a project charter with clear objectives

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 3 minutes
  5. Mid to senior

    Two weeks before a new payroll system goes live, the internal audit team says it was never consulted and asks for the launch to be held until it has tested the controls. What went wrong, and what do you do now?

    What it tests
    Recovering from a missed stakeholder with power: engaging them at once, finding the smallest safe path to launch, and fixing the identification process that missed them.
    First step
    Meet the audit team within a day, without arguing about the past. Ask exactly which controls they must test and how long each test takes, and bring the evidence the project already has, so the hold can be as short and as targeted as possible.
    Follow-ups

    From the lesson Identifying and analysing stakeholders

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  6. Senior to staff

    A department head whose budget your project draws on opposes it and skips every meeting you invite them to. Their deputy attends but cannot decide anything. How do you plan your engagement with this person?

    What it tests
    Analysing a high-power, resistant stakeholder, finding the cause of the resistance and planning one-to-one engagement and escalation without damaging the relationship.
    First step
    Stop relying on group meetings. Ask for a short one-to-one meeting, framed around their concerns, not your project, and listen for the cause: lost budget, extra work for their staff or a past project that failed them. Record their current level as resistant and the level you need, at least neutral.
    Follow-ups

    From the lesson Identifying and analysing stakeholders

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  7. Mid to senior

    A new booking system serves both the outpatient and the radiology departments of a hospital. Each director insists on being accountable for the go-live decision, and neither will accept being consulted. How do you resolve it?

    What it tests
    Applying the one-A rule to a contested decision, separating ownership of the decision from a voice in it, and taking an unresolved conflict to the right level.
    First step
    Meet each director separately and ask what they need to be sure of before go-live. Usually each wants a veto on their own department's readiness, which can be given as a named readiness check without making them both owners of the one decision.
    Follow-ups

    From the lesson RACI charts, decision rights and escalation

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes
  8. Senior to staff

    On your programme every change, even a 10 thousand purchase or a renamed report, waits for a steering committee that meets once a month. Teams sit idle for weeks. What do you change, and how do you get the committee to agree?

    What it tests
    Designing decision rights with thresholds by impact, delegating small decisions without losing control, and persuading a governance body to delegate.
    First step
    Collect the last three months of decisions with their cost, their effect on milestones and how long each waited. Most will be small; show the committee how many weeks of waiting they caused, then propose thresholds that keep every large decision with the committee.
    Follow-ups

    From the lesson RACI charts, decision rights and escalation

    Model answer, Pro.

    In the answer:

    • Model answer
    • Follow-up answers
    • Common mistakes
    • Rubric
    • Variants
    • about 2 minutes

All Project Management & Agile interview questions · The Project Management & Agile track

Quick answers and tool search

Type to search tools or to get a quick answer, for example 18% of 2500. Use the up and down arrow keys to move through the results, Enter to choose, and Escape to close.